Filter by category
Filter by Date
Electricity market suspension change of pricing regime
Electricity market suspension change of pricing regime
Refer initial AEMO Electricity Market Notice 107545
The Spot Market remains suspended in the following regions with the following pricing regimes from Trading Interval 0435 hrs on 23 April 2023 until further notice:
Victoria from Market Suspension Schedule Pricing to Dispatch Pricing (refer NER clause 3.14.5(d))
The cause of the original issue which affected all Victoria SCADA has not yet been resolved and may still influence market processes, hence, the Spot Market suspension will continue at this stage. However, AEMO has determined it is practicable to dispatch and price the suspended region in accordance with NER clauses 3.8 and 3.9.
Relevant Market Notices issued under this suspension:
107545
Manager NEM Real Time Operation
Declaration of electricity market suspension
Declaration of electricity market suspension
AEMO declares the spot market suspended in Victoria with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1620 hrs on 22 April 2023 until further notice.
Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.
Refer market notice 107544
Manager NEM Real Time Operation
Declaration of electricity market resumption
Declaration of electricity market resumption
Refer initial AEMO Electricity Market Notice 106784
AEMO declares that the suspension of the spot market in New South Wales will end at 2110 hrs on 17 March 2023.
Failure of SCADA systems in NSW have been resolved.
Relevant Market Notices issued under this suspension:
106784
Manager NEM Real Time Operations
Declaration of electricity market suspension
Declaration of electricity market suspension
AEMO declares the spot market suspended in New South Wales with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 2015 hrs on 17 March 2023 until further notice.
Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.
AEMO has determined that it has become impossible to operate the spot market in accordance with the provisions of the Rules due to ? Failure of SCADA systems in NSW.
Manager NEM Real Time Operation
Request for Generator Recall Information for 16/03/2023 for NSW Region
Refer to AEMO Electricity Market Notice 106497.
Please provide Generator Recall Information for 16/03/2023 by 1100 hrs AEST on 14/03/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for 16/03/2023 for QLD Region
Refer to AEMO Electricity Market Notice 106498.
Please provide Generator Recall Information for 16/03/2023 by 1100 hrs AEST on 14/03/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Request for Generator Recall Information for 03/02/2023 for QLD Region
Refer to AEMO Electricity Market Notice 105433.
Please provide Generator Recall Information for 03/02/2023 by 1700 hrs AEST on 01/02/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
Cancellation: Protected event advice - South Australia region.
AEMO has identified that the conditions of the following protected event are no longer met.
Protected event: the loss of multiple transmission elements causing generation disconnection in the South Australia region during periods where destructive wind conditions are forecast by the Bureau of Meteorology.
Cancellation: 2100 hrs 30/10/2022
Constraint set revoked: I-VS_250
Refer AEMO Electricity Market Notice 102723
Manager NEM Real Time Operations
Final - Market suspension - FCAS prices
In accordance with Market notices 99065 and 99070, the zero ancillary services prices to TIs 0805 - 0900 on 23 June 2022 for all services in all regions have been replaced with the corresponding ROP values for each TI, service, and region.
Manager NEM Real Time Operations