CHG0041157 : Emergency System Maintenance - Electricity MMS Production Site Transfer (From NSW to QLD)
Notification issued to: Market Notice
Notification Type: Emergency
Change Type: Emergency
Service/ Component: EMMS
Change Title: Emergency System Maintenance - Electricity MMS Production Site Transfer (From NSW to QLD)
Outage Start Date & Time: 10/11/2016 14:00:00 AEST
Outage End Date & Time: 10/11/2016 15:30:00 AEST
Change Description:
There is an emergency site transfer planned at 14:00 to mitigate an infrastructure problem. Dispatch cycles may be missed during the transfer. MegaVar dispatch screen will be unavailable for a short period during this time
Environment: Production
Participant Impact and Requirements:
Awareness of Site Transfer. There may be some interruptions to the service during this window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NB. AEST (Australian Eastern Standard Time) is equivalent to UTC + 10 hrs.
CHG0041062 : Planned System Change - MSATS Production Year-End 2016 - Release 46.86 - Stage 2
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution
Change Title: Planned System Change - MSATS Production Year-End 2016 - Release 46.86 - Stage 2
Change Start Date & Time: 16/11/2016 17:30:00 AEST
Change End Date & Time: 16/11/2016 19:30:00 AEST
Outage Start Date & Time: 16/11/2016 17:30:00 AEST
Outage End Date & Time: 16/11/2016 19:30:00 AEST
Change Description:
The MSATS Production system will be upgraded with the MSATS 46.86 Year-end Release as per the change notice 933A issued on 12th August 2016.
Note: This release implements the latest version of Enumerations (7.0).
Environment: Production
Participant Impact and Requirements:
Awareness of this Outage. MSATS Production environment will be unavailable during the outage times mentioned above.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0040814 : Planned System Outage - Software Upgrade - QLD MarketNet VPN POP
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: QLD MARKETNET POP
Change Title: Planned System Outage - Software Upgrade - QLD MarketNet VPN POP
Change Start Date & Time: 16/11/2016 08:00:00 AEST
Change End Date & Time: 16/11/2016 14:00:00 AEST
Outage Start Date & Time: 16/11/2016 08:30:00 AEST
Outage End Date & Time: 16/11/2016 12:00:00 AEST
Change Description:
Software Upgrade is performed to increase the reliability and stability of the QLD MarketNet VPN POP.
Purpose: Software Upgrade is performed to increase the reliability and stability of the QLD MarketNet VPN POP.
Environment: Production
Participant Impact and Requirements:
All MarketNet access via the QLD VPN POP
IPWAN - 1 x 30 second disruptions.
Redirect VPN access via the NSW VPN POP:
- Site-to-Site: 202.44.78.10
- VPN Variable: 202.44.78.8
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0040831: Planned System Maintenance to Declared Wholesale Gas Market Production Systems
Change Number: CHG0040831
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Declared Wholesale Gas Market
Change Title: Planned System Maintenance to Declared Wholesale Gas Market Production Systems
Change Start Date & Time: 08/11/2016 18:30:00 AEST
Change End Date & Time: 08/11/2016 20:30:00 AEST
Outage Start Date & Time: 08/11/2016 18:30:00 AEST
Outage End Date & Time: 08/11/2016 20:30:00 AEST
Change Description:
Maintenance is to be performed on the Production Declared Wholesale Gas Market Systems to increase the reliability, security and stability. During the maintenance, there will be an outage as per the times mentioned.
Environment: Production
Participant Impact and Requirements:
The following impacts are expected during the maintenance window:
- All access to theMIBB & WEX Systems will be unavailable.
- All access to the MIBB for the NSW/ACT Retail Gas Market Participants will be unavailable.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0040836: Planned System Maintenance - GFRC Production Systems including B2B hub - Norwest
Change Number: CHG0040836
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas - Retail
Change Title: Planned System Maintenance - GFRC Production Systems including B2B hub - Norwest
Change Start Date & Time: 13/11/2016 10:00:00 AEST
Change End Date & Time: 13/11/2016 14:00:00 AEST
Outage Start Date & Time: 13/11/2016 10:00:00 AEST
Outage End Date & Time: 13/11/2016 14:00:00 AEST
Change Description:
Planned maintenance activities will be performed on the Production Gas Full Retail Contestability and GAS B2B Systems. There will be no access to the Production Gas Full Retail Contestability and Gas B2B systems for the duration of the outage period
Environment: Production
Participant Impact and Requirements:
The following impacts are expected during this maintenance:
- All access to the VIC & QLD RETAIL GFRC Production Systems will be unavailable.
- All access to the GasB2B hub will be unavailable.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0040769: Planned Outage - Completed - Market Settlement and Transfer Solutions (MSATS) - Site Transfer - QLD to NSW
Change Number: CHG0040769
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/ Component: Market Settlement and Transfer Solution
Change Title: Planned Outage - Market Settlement and Transfer Solutions (MSATS) - Site Transfer - QLD to NSW
Change Description:
System transferred successfully to NSW site
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0040434: Planned System Outage to OPDMS to deploy new version to Production environment - COMPLETED
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/ Component: Operations and Planning Data Management
Change Title: Planned System Outage to OPDMS to deploy new version to Production environment
Change Description:
All ok. Ausnet monitors in Production HSM.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0040769: Planned Outage - Market Settlement and Transfer Solutions (MSATS) - Site Transfer - QLD to NSW
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Settlement and Transfer Solution
Change Title: Planned Outage - Market Settlement and Transfer Solutions (MSATS) - Site Transfer - QLD to NSW
Change Start Date & Time: 02/11/2016 17:30:00 AEST
Change End Date & Time: 02/11/2016 19:30:00 AEST
Outage Start Date & Time: 02/11/2016 17:30:00 AEST
Outage End Date & Time: 02/11/2016 19:30:00 AEST
Change Description:
MSATS Production Site Transfer will be carried out from QLD to NSW Site to allow maintenance work on the other site.
Environment: Production
Participant Impact and Requirements:
Access to all parts of the Electricity MSATS system may be interrupted during the outage period. Access should be attempted outside these times.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0040779: Planned System Maintenance - Declared Wholesale Gas Market System (DWGM) Pre-production
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Socket Application
Change Title: Planned System Maintenance - Declared Wholesale Gas Market System (DWGM) Pre-production
Change Start Date & Time: 31/10/2016 10:30:00 AEST
Change End Date & Time: 31/10/2016 11:00:00 AEST
Outage Start Date & Time: 31/10/2016 10:30:00 AEST
Outage End Date & Time: 31/10/2016 11:30:00 AEST
Change Description:
Maintenance activity is to be performed on the Declared Wholesale Gas Market System (DWGM) in Pre-production to increase reliability, security and stability of the system.
Environment: Pre-Production
Participant Impact and Requirements:
All access to the Declared Wholesale Gas Market (DWGM) Pre-production will be unavailable during the outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.