53570NON-CONFORMANCE31/05/2016 11:55:12 AM

NON-CONFORMANCE Region NSW1 Tuesday, 31 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 31 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: MP2
Duration: 31/05/2016 11:40 to 31/05/2016 11:55
Amount: -31 MW
Constraint: NC-N_MP2

Auto-generated on behalf of Manager NEM Real Time Operations
53569NON-CONFORMANCE31/05/2016 07:45:22 AM

NON-CONFORMANCE Region QLD1 Tuesday, 31 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 31 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: BRAEMAR2
Duration: 31/05/2016 07:30 to 31/05/2016 07:45
Amount: -13 MW
Constraint: NC-Q_BRAEMAR2

Auto-generated on behalf of Manager NEM Real Time Operations
53568NON-CONFORMANCE31/05/2016 07:45:09 AM

NON-CONFORMANCE Region QLD1 Tuesday, 31 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 31 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: BRAEMAR1
Duration: 31/05/2016 07:15 to 31/05/2016 07:45
Amount: -13 MW
Constraint: NC-Q_BRAEMAR1

Auto-generated on behalf of Manager NEM Real Time Operations
53567NON-CONFORMANCE31/05/2016 12:50:17 AM

NON-CONFORMANCE Region VIC1 Tuesday, 31 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 31 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: HWPS3
Duration: 31/05/2016 00:45 to 31/05/2016 00:50
Amount: 10 MW
Constraint: NC-V_HWPS3

Auto-generated on behalf of Manager NEM Real Time Operations
53564NON-CONFORMANCE30/05/2016 08:45:10 AM

NON-CONFORMANCE Region NSW1 Monday, 30 May 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 30 May 2016

AEMO declared a schedule generating unit non-conforming

Unit: SITHE01
Duration: 30/05/2016 06:30 to 30/05/2016 08:45
Amount: 23 MW
Constraint: NC-N_SITHE01

Auto-generated on behalf of Manager NEM Real Time Operations
53563RECLASSIFY CONTINGENCY30/05/2016 03:43:34 AM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin 857 and 858 275 kV Lines in Queensland due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin 857 and 858 275 kV Lines in Queensland due to Lightning.

Refer to AEMO Electricity Market Notice no. 53562


There is no longer any Lightning activity in the vicinity of the Ross - Chalumbin 857 and 858 275 kV Lines.

AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0345 hrs 30/05/2016.


Manager NEM Real Time Operations
53562RECLASSIFY CONTINGENCY30/05/2016 01:20:56 AM

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin 857 and 858 275 kV Lines in Queensland due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin 857 and 858 275 kV Lines in Queensland due to Lightning.

Lightning is occurring near the Ross - Chalumbin 857 and 858 275 kV Lines.

AEMO considers the simultaneous trip of those circuits to now be more likely.

Therefore AEMO has reclassified this as a credible contingency event from 0120 hrs 30/05/2016 until further notice.


Manager NEM Real Time Operations
53558RECLASSIFY CONTINGENCY29/05/2016 01:24:45 PM

Cancellation Reclassification of a Non Credible Contingency Event: Mudgeeraba Terranora 757 and 758 110 kV Lines in Queensland due to Bushfire.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Reclassification of a Non Credible Contingency Event: Mudgeeraba Terranora 757 and 758 110 kV Lines in Queensland due to Bushfire.
Refer AEMO Electricity Market Notice 53557
Constraint Set I-TE_ZERO to be revoked.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits to be a credible contingency event from 1315 hrs 29 May 2016

Manager NEM Real Time Operations
53557RECLASSIFY CONTINGENCY29/05/2016 10:24:32 AM

Reclassification of a Non Credible Contingency Event: Mudgeeraba Terranora 757 and 758 110 kV Lines in Queensland due to Bushfire.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non Credible Contingency Event: Mudgeeraba Terranora 757 and 758 110 kV Lines in Queensland due to Bushfire.

A Bushfire exists in the vicinity of the Mudgeeraba Terranora 757 and 758 110 kV Lines in Queensland due to Bushfire.

AEMO has reclassified the simultaneous trip of those circuits to be a credible contingency event from 1015 hrs 29 May 2016 until further notice.

Constraint Set I-TE_ZERO invoked.


Manager NEM Real Time Operations