Market Notices

54710RESERVE NOTICE12/08/2016 11:39:05 AM

Cancellation of the Actual (LOR2) condition in the South Australia region.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Actual (LOR2) condition in the South Australia region.

Refer to AEMO Electricity Market Notice No. 54693

The Actual LOR2 condition in the South Australia Region is cancelled at 1130 hrs Friday, 12 August 2016

Manager NEM Real Time Operations
54709GENERAL NOTICE12/08/2016 07:42:18 AM

Outage cancelled - Planned outage of Moorabool to Mortlake PS 500kV line in Victoria region from 21/08/2016 0630 hrs to 21/08/2016 1800 hrs

AEMO ELECTRICITY MARKET NOTICE.

** The outage has been cancelled by Ausnet **

This market notice is FOR INFORMATION ONLY.

The Moorabool to Mortlake PS 500kV line in Victoria Region is planned out of service from 0630 hrs on 21 August 2016 to 1800 hrs on 21 August 2016.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-V-MLMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLMO

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.

Operations Planning
54708GENERAL NOTICE12/08/2016 07:35:11 AM

Outage cancelled - Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 20/08/2016 0630 hrs to 20/08/2016 1800 hrs

AEMO ELECTRICITY MARKET NOTICE.

** The outage has been cancelled by Ausnet **

This market notice is FOR INFORMATION ONLY.

The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0630 hrs on 20 August 2016 to 1800 hrs on 20 August 2016.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-V_MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.

Edmund Hon
AEMO Operations
54693RESERVE NOTICE10/08/2016 04:30:44 PM

Actual LOR2 South Australia Region

AEMO ELECTRICITY MARKET NOTICE

Actual LOR2 South Australia Region
Refer AEMO Electricity Market Notice 54624
An actual LOR2 condition has been declared for the South Australia region from 1630 hrs until further notice during a planned outage of Heywood No1 500 kV bus in the Victoria region
If a credible contingency event occurs in this period the South Australia region would separate from the rest of the NEM and is likely to result in interruptions to power supplies.
There are sufficient capacity reserves in the South Australia region to meet electricity demand but it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing power interruptions.

Manager NEM Real Time Operations
54689RESERVE NOTICE10/08/2016 11:43:58 AM

Cancellation of the Actual (LOR2) condition in the South Australia region

AEMO ELECTRICITY MARKET NOTICE
Cancellation of the Actual (LOR2) condition in the South Australia region
Refer to AEMO Electricity Market Notice No. 54687
The Actual LOR2 condition in the South Australia Region is cancelled at 1135 hrs 10/8/16

Manager NEM Real Time Operations

54687RESERVE NOTICE10/08/2016 07:52:50 AM

Actual LOR2 South Australia Region

AEMO ELECTRICITY MARKET NOTICE

Actual LOR2 South Australia Region
Refer AEMO Electricity Market Notice 54624
An actual LOR2 condition has been declared for the South Australia region from 0745 hrs until further notice during a planned outage of Heywood No1 500 kV bus in the Victoria region
If a credible contingency event occurs in this period the South Australia region would separate from the rest of the NEM and is likely to result in interruptions to power supplies.
There are sufficient capacity reserves in the South Australia region to meet electricity demand but it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing power interruptions.

Manager NEM Real Time Operations






54686GENERAL NOTICE10/08/2016 07:51:24 AM

Planned outage of Heywood No.2 500kV Bus in Victoria region from 06/09/2016 0700 hrs to 09/09/2016 1700 hrs

AEMO ELECTRICITY MARKET NOTICE.

This market notice is FOR INFORMATION ONLY.

The Heywood No.2 500 kV busbar in Victoria Region is planned out of service from 0700 hrs on 6 September 2016 to 1700 hrs on 9 September 2016. During this outage, Heywood 500/275 kV M2 transformer will be off-loaded and Heywood - Mortlake - Alcoa Portland No.2 500 kV line will be opened at Heywood.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-I_HYSE (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-HYTX_M12
V-HY_500BUS

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.

Edmund Hon
AEMO Operations
54685GENERAL NOTICE10/08/2016 07:43:29 AM

Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 02/09/2016 0700 hrs to 02/09/2016 1700 hrs

AEMO ELECTRICITY MARKET NOTICE.

This market notice is FOR INFORMATION ONLY.

The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0700 hrs on 2 September 2016 to 1700 hrs on 2 September 2016.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.

Edmund Hon
AEMO Operations
54684GENERAL NOTICE10/08/2016 07:40:15 AM

Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 31/08/2016 0700 hrs to 31/08/2016 1700 hrs

AEMO ELECTRICITY MARKET NOTICE.

Update to MN 54682 - Subject updated accordingly. Content of the market notice didn't change.

This market notice is FOR INFORMATION ONLY.

The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0700 hrs on 31 August 2016 to 1700 hrs on 31 August 2016.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.

Edmund Hon
AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm