PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 17/06/2022
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98213 has been updated at 1730 hrs to the following:
[1.] From 0730 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 477 MW at 0730 hrs.
[2.] From 0900 hrs 17/06/2022 to 0930 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 65 MW at 0900 hrs.
[3.] From 1530 hrs 17/06/2022 to 1630 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 451 MW at 1600 hrs.
[4.] From 1700 hrs 17/06/2022 to 0230 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 3026 MW at 2000 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0700 hrs on 17/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region beginning on 17/06/2022
The Forecast LOR3 condition in the VIC region advised in AEMO Electricity Market Notice No. 98212 has been updated at 1700 hrs to the following:
[1.] From 0730 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 530 MW at 0730 hrs.
[2.] From 0900 hrs 17/06/2022 to 0930 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 116 MW at 0900 hrs.
[3.] From 1530 hrs 17/06/2022 to 1630 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 495 MW at 1600 hrs.
[4.] From 1700 hrs 17/06/2022 to 0100 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1707 MW at 2000 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0700 hrs on 17/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region beginning on 17/06/2022
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 98211 has been updated at 1700 hrs to the following:
[1.] From 0730 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 500 MW at 0730 hrs.
[2.] From 0900 hrs 17/06/2022 to 0930 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 116 MW at 0900 hrs.
[3.] From 1600 hrs 17/06/2022 to 1630 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 44 MW at 1600 hrs.
[4.] From 1700 hrs 17/06/2022 to 2300 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 553 MW at 1800 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0700 hrs on 17/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 17/06/2022
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98200 has been updated at 1630 hrs to the following:
[1.] From 0700 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 669 MW at 0730 hrs.
[2.] From 0900 hrs 17/06/2022 to 0930 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 297 MW at 0900 hrs.
[3.] From 1530 hrs 17/06/2022 to 1630 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 586 MW at 1600 hrs.
[4.] From 1700 hrs 17/06/2022 to 0230 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 2994 MW at 2000 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0630 hrs on 17/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region beginning on 17/06/2022
The Forecast LOR3 condition in the VIC region advised in AEMO Electricity Market Notice No. 98201 has been updated at 1630 hrs to the following:
[1.] From 0700 hrs 17/06/2022 to 0930 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 832 MW at 0730 hrs.
[2.] From 1530 hrs 17/06/2022 to 1630 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 586 MW at 1600 hrs.
[3.] From 1700 hrs 17/06/2022 to 0100 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1799 MW at 2000 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0630 hrs on 17/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region beginning on 17/06/2022
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 98203 has been updated at 1630 hrs to the following:
[1.] From 0700 hrs 17/06/2022 to 0930 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 816 MW at 0730 hrs.
[2.] From 1530 hrs 17/06/2022 to 1630 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 224 MW at 1600 hrs.
[3.] From 1700 hrs 17/06/2022 to 0100 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 758 MW at 1900 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0630 hrs on 17/06/2022.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the QLD Region on 16/06/2022
The Forecast LOR3 condition in the QLD region advised in AEMO Electricity Market Notice No. 98138 is cancelled at 1530hrs 17/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region beginning on 17/06/2022
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 98194 has been updated at 1600 hrs to the following:
[1.] From 0730 hrs 17/06/2022 to 1030 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 703 MW at 0800 hrs.
[2.] From 1500 hrs 17/06/2022 to 0100 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 758 MW at 2000 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0700 hrs on 17/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region beginning on 17/06/2022
The Forecast LOR3 condition in the VIC region advised in AEMO Electricity Market Notice No. 98193 has been updated at 1600 hrs to the following:
[1.] From 0730 hrs 17/06/2022 to 1030 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 765 MW at 0900 hrs.
[2.] From 1500 hrs 17/06/2022 to 0100 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1804 MW at 2000 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0700 hrs on 17/06/2022.
AEMO Operations