105822POWER SYSTEM EVENTS13/02/2023 02:34:40 PM

Non-credible contingency event - Qld Region - 13/02/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - Qld Region - 13/02/2023

At 1402 hrs 13/02/2023 the H77 Columboola - H76 Wandoan South No. 8891 and No. 8892 275 kV Lines tripped, also affecting supply west of H79 Yuleba North and H80 Eurombah.

AEMO did not instruct load shedding.

Approximately 390 MW of Load interrupted and 114 MW of Generation interrupted.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
105653POWER SYSTEM EVENTS06/02/2023 09:39:29 AM

Non-credible contingency event - Qld Region - 03/02/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - Qld Region - 03/02/2023

At 1722 hrs 03/02/2023 the Kareeya Power Station Unit 1, Unit 2 and Unit 4 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
104357POWER SYSTEM EVENTS11/12/2022 01:34:36 PM

Update - Non-credible contingency event - Vic region - 11/12/2022

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - Vic region - 11/12/2022

Refer AEMO ELECTRICITY MARKET NOTICE 104353

At 1157 hrs the Kerang - Wemen - Red Cliffs 220 kV Line and the Kiamal Solar Farm STX transformer (Kiamal synchronous condenser) tripped.

AEMO did not instruct load shedding.

AEMO has been advised of disconnection of bulk electrical load (27 MW)

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
104353POWER SYSTEM EVENTS11/12/2022 01:11:07 PM

Non-credible contingency event - Vic region - 11/12/2022

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - Vic region - 11/12/2022

At 1157 hrs the Kerang - Wemen - Red Cliffs 220 kV Line and the Kiamal Solar Farm STX transformer (Kiamal synchronous condenser) tripped.

AEMO did not instruct load shedding.

AEMO is still waiting to be advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
103961POWER SYSTEM EVENTS25/11/2022 08:32:50 PM

Update - Vulnerable lines in Qld region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in Qld region

Refer to AEMO Electricity Market Notice 103958 and 103959

At 1913 hrs Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV Lines tripped and auto-reclosed.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV lines to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
103958POWER SYSTEM EVENTS25/11/2022 07:40:37 PM

Non-credible contingency event - Qld region - 25/11/2022

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - Qld region - 25/11/2022

At 1913 hrs the Chalumbin - Turkinje 7165 and 7166 132 kV Lines tripped and auto-reclosed.

AEMO did not instruct load shedding.

Approximately 75 MW of load was interrupted during the auto-reclose time.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
103900POWER SYSTEM EVENTS23/11/2022 06:29:16 PM

Update - Non-credible contingency event - SA region - 12/11/2022

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 12/11/2022

Refer AEMO ELECTRICITY MARKET NOTICE 103066

At 1803 hrs 19/11/2022, Tailem Bend - South East No 1 275 kV Line was returned to service.

At 1805 hrs 23/11/2022, Tailem Bend - South East No 2 275kV Line was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
103664POWER SYSTEM EVENTS19/11/2022 07:10:59 PM

Update - Significant power system event - 12/11/2022

AEMO ELECTRICITY MARKET NOTICE.

Update - Significant power system event - 12/11/2022

Refer AEMO Electricity Notice 103067

At 1803 hrs 19/11/2022, Tailem Bend - South East No 1 275 kV Line was returned to service

South Australia is now re-synchronised with the Eastern NEM.

The following constraints sets have been revoked at 1840 hrs;
SA_ESTN_LG_ISLE
SA_ISLE_LB_FFR_ZERO
F-SA_ESTN_ISLE_REG
S-X_BC_CP

Refer to AEMO Network Outage Schedule for further information.

Manager NEM Real Time Operations
103504PRICE ADJUSTMENT18/11/2022 12:36:57 PM

[EventId:202211170915_confirmed] Prices for interval 17-Nov-2022 09:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1234 hrs on 18 November 2022

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2022 09:15.

In accordance with Market Notice 103363 AEMO has reviewed this trading interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
RAISE60SEC
NSW1 $1.60 $2.00
QLD1 $1.60 $2.00
TAS1 $1.60 $2.00
VIC1 $1.60 $2.00
RAISEREG
NSW1 $29.67 $37.29
QLD1 $29.67 $37.29
TAS1 $13.51 $11.86
VIC1 $29.67 $37.29


This is an AEMO autogenerated Market Notice.