The consultation process is outlined below. Dates are indicative only and subject to change.
Process Stage | Date |
---|---|
Publication of Procedure Change Proposal | 16 July 2025 |
Closing date for submissions on Procedure Change Proposal | 13 August 2025 |
Publication of Procedure Change Report | 26 August 2025 |
Proposed commencement of amended Procedure | 26 August 2025 |
Procedure Change Proposal
Electricity System and Market Rules – Clause 2.10
Date of Notice: 16 July 2025
Matter under Consultation
AEMO has commenced the Procedure Change Process to propose the following new WEM Procedure: Short Term PASA. The Procedure outlines the processes AEMO follows in preparing and conducting the Short Term PASA, including:
- the information to be included when publishing the Short Term PASA;
- the information that AEMO requires from Rule Participants;
- the process by which AEMO will use any information developed by AEMO in performing its functions to prepare the Short Term PASA;
- the timing and frequency for which AEMO will conduct and publish the Short Term PASA;
- the granularity of information to be included, and any additional demand forecast information to be published.
On 6 February 2025 the SEO replaced the Wholesale Market Objectives under section 3A of the Electricity Industry Act 2004. Following an assessment, AEMO considers the proposed changes are consistent with the SEO.
Procedure Change Proposal documents
Invitation to Make Submissions
AEMO invites written submissions on this Procedure Change Proposal, including any alternative or additional proposals you consider may improve the procedure or better meet the SEO under section 3A of the Electricity Industry Act 2004.
Please identify any parts of your submission that you wish to remain confidential, and explain why. AEMO may still publish that information if it does not consider it to be confidential, but will consult with you before doing so.
When making a claim for confidentiality, AEMO encourages respondents to familiarise themselves with Chapter 10 of the Wholesale Electricity Market Rules, which imposes obligations in respect to the release of documents.
Meetings
Before the closing date for submissions, you may request a meeting with AEMO to discuss the issues and proposed changes raised in the Procedure Change Proposal, stating why you consider a meeting is necessary or desirable.
If appropriate, meetings may be held jointly with other stakeholders. Subject to confidentiality restrictions, AEMO will generally make details of matters discussed at a meeting available to other stakeholders, and may publish those details.
Closing Date and Time
Submissions in response to this Procedure Change Proposal should be sent by email to WA.Marketdevelopment@aemo.com.au, to reach AEMO by 5.00 pm (AWST) on 13 August 2025.
All submissions must be in electronic format (pdf or Microsoft Word). Submissions should use the Procedure Change Submission form available on this page.
AEMO is not obliged to consider submissions received after the closing date and time. Any late submissions should explain the reason for delay and the detriment to you if AEMO does not consider your submission.
Publication
All submissions will be published on AEMO’s website. Confidential information will not be published, other than as specified above.