Timeline
-
Publication of the approach paper12 October 2022
-
Publication of the draft report3 March 2023
-
Publication of addendum to the draft report4 April 2023
-
Consultation on the draft report closes20 April 2023
-
Consultation on addendum to the draft report closes23 May 2023
-
Publication of Update Report Part 1 including draft NER amendments26 July 2023
-
Consultation closure on Update Report Part 123 August 2023
-
Publication of the final reportDecember 2023
Key contact
Overview
AEMO has completed its first five-yearly review of the technical requirements for National Electricity Market (NEM) connection, in NER Schedules 5.2, 5.3 and 5.3a through its Access Standards Review (Review). The schedules set out technical requirements for connection of generation (and, from June 2024, integrated resource systems), loads and market network service facilities, respectively.
The three National Electricity Rules (NER) schedules set out the access standards that may be agreed for the connection of relevant plant to NEM transmission and distribution networks by registered participants and some other parties, to establish required levels of plant capability or performance in relation to specified technical requirements. For most requirements, access may be negotiated between an automatic access standard (AAS) and a minimum access standard (MAS). A number of requirements also specify negotiating parameters and general conditions to be met in all cases.
National Electricity Rules requirements
AEMO conducted the Review under NER 5.2.6A of the NER, to assess the need for amendment to the technical requirements. Under NER 5.2.6A(a), AEMO must conduct a review of some or all of the technical requirements in NER Schedules 5.2, 5.3 and 5.3a once in every five-year period to assess whether those requirements should be amended. NER 5.2.6A was introduced in October 2018, and this was the first review under that provision.
In conducting this review, among other things, AEMO is required to have regard to:
1. the national electricity objective
2. the need to achieve and maintain power system security
3. changes in power system conditions; and
4. changes in technology and capabilities of facilities and plant.
Outcomes
The final report makes recommendations to address 44 issues in NER Schedules 5.2, 5.3 and 5.3a which were identified by AEMO and its stakeholders over the course of the Review. Stakeholders have included approximately 250 individuals across over 100 organisations representing Network Service Providers, Original Equipment Manufacturers (OEMs), developers and large load customers.
Final recommendations, once given effect through a subsequent NER amendment process, will realise a range review objectives, which include:
- aligning standards with best power system performance;
- improving power system resilience;
- streamlining the connections process; and
- accommodating new technology associated with large loads, grid-forming inverters, synchronous condensers and HVDC links.
Next steps
On publication of the final report, AEMO will write to the AEMC to confirm that AEMO intends to submit rule change proposals, and request the AEMC to consider the fast track process for the majority of its rule changes arising from the Schedule 5.2 and 5.3a recommendations. Other recommendations would then propose a standard rule change process seeking to make other final recommendations.
Engagement
Prior to the final report, AEMO published the following key documents in the Review:
- An approach paper (published 12 October 2022) that described the matters that AEMO proposed to review.
- A draft report (published 3 March 2023) setting out its draft recommendations for amendments to technical requirements of NER Schedules 5.2 and 5.3a, and the reasons for its recommendations. 18 stakeholders made submissions on this report.
- An addendum to the draft report (published 4 April 2023) setting out its draft recommendations for amendments to technical requirements of NER Schedule 5.3, and the reasons for its recommendations. 11 stakeholders made submissions on this report
- An update report (published 26 July 2023) setting out revised recommendations for amendments to technical requirements of NER Schedules 5.2 and 5.3a, the reasons for its recommendations, and initial proposed drafting of NER amendments that could give effect to the revised recommendations. 23 stakeholders made submissions on this report.
Stakeholder feedback on the above documents has informed AEMO’s final recommendations.
Engagement on Update Report
AEMO facilitated a public webinar forum on Wednesday 9 August 2023 to discuss the recommendations set out in its Update Report.
The webinar provided the:
- current status of the Review;
- an overview of revised recommendations of the Update Report; and t (Part 1)
- the opportunity for stakeholders to raise questions or issues regarding the revised recommendations.
Engagement on Draft Report
AEMO facilitated a public webinar forum on Wednesday 12 April 2023 to discuss the recommendations set out in its Draft Report. The webinar provided was facilitated to provide background, approach and current status of the Review; overview of recommendations made by the draft report and addendum; and the opportunity for stakeholders to raise questions or issues regarding the draft recommendations.
Documents
-
Approach paper
-
Draft report
-
Draft Report Addendum
-
Update Report
-
Final report
-
03/03/2023
Draft report - AEMO review of technical requirements for connection under Schedules 5.2, 5.3 and 5.3a of the National Electricity Rules
1.65 MB -
03/03/2023
Stakeholder feedback template for Schedule 5.2 and 5.3a recommendations (optional completion)
60.5 KB -
14/04/2023
Presentation slides from 14 April 2023
1.09 MB
Written submissions from stakeholders on draft report (close 20 April 2023)
AEMO received 18 submissions on the technical requirements and recommendations in the primary draft report (that is relating to Schedules 5.2 and 5.3a).
Submissions were received from:
-
04/05/2023
AGL
120.21 KB -
04/05/2023
Amp Power
215.11 KB -
04/05/2023
APD
283.26 KB -
04/05/2023
AusNet
819.21 KB -
04/05/2023
Bo Yin
181.43 KB -
04/05/2023
CEC
657.13 KB -
04/05/2023
CPSA
189.05 KB -
04/05/2023
Energy Queensland
147.48 KB -
04/05/2023
Goldwind Australia
139.37 KB -
04/05/2023
Hitachi Energy
226.24 KB -
24/05/2023
Hydro Tasmania
217.14 KB -
04/05/2023
Marinus Link
346.13 KB -
04/05/2023
Rod Hughes Consulting
108.87 KB -
04/05/2023
TasNetworks
693.41 KB -
04/05/2023
Total Eren
192.65 KB -
04/05/2023
Transgrid
283.31 KB
Late submissions were received from:
Written submissions from stakeholders on addendum to draft report (close 23 May 2023)
AEMO received 11 submissions on the technical requirements and recommendations in the addendum to the draft report (that is relating to Schedule 5.3).
Submissions were received from:
A late submission was received from:
-
26/07/2023
Draft Recommendations Update Report – NER Schedules 5.2 & 5.3a
890.5 KB -
26/07/2023
Appendix A1. Stakeholder consultation analysis and revised recommendations
1.21 MB -
26/07/2023
Appendix A2. Draft NER amendments
2.68 MB -
26/07/2023
Stakeholder feedback template for Schedule 5.2 and 5.3a revised recommendations (optional completion)
63.74 KB
Written Submissions
-
06/09/2023
Amp Power Australia
211.71 KB -
06/09/2023
AusNet
525.22 KB -
06/09/2023
Bo Yin
206.09 KB -
06/09/2023
Catarpillar
210.53 KB -
06/09/2023
CEC
409.08 KB -
06/09/2023
CPSA
93.22 KB -
06/09/2023
CTLab
348.62 KB -
06/09/2023
ENA
134.66 KB -
06/09/2023
Energy Queensland
199.45 KB -
06/09/2023
Huawei Australia
209.38 KB -
06/09/2023
Hydro Tasmania
248.33 KB -
06/09/2023
NEOEN
232.36 KB -
06/09/2023
Powerlink
626.6 KB -
06/09/2023
Powerlink - Cover Letter
439.6 KB -
06/09/2023
SAPN
289.47 KB -
06/09/2023
Solar Turbines Sagl
293.77 KB