NON-CONFORMANCE Region NSW1 Monday, 12 May 2025
NON-CONFORMANCE NSW1 Region Monday, 12 May 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 12/05/2025 15:05 to 12/05/2025 15:10
Amount: -9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 126997
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0930 hrs 13/05/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 12/05/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1030 hrs to 1230 hrs 15/05/2025.
The forecast capacity reserve requirement is 438 MW.
The minimum capacity reserve available is 401 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 13/05/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/05/2025
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/05/2025
Refer Market Notice 126981
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1600 hrs 11/05/2025.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 10/05/2025
Cancellation - AEMO Intervention Event - SA region 10/05/2025
Refer to Market Notice 126977
The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs on 11/05/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 126978
Direction is cancelled from: 1530 hrs 11/05/2025
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 126979
Direction is cancelled from: 1500 hrs 11/05/2025
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 12/05/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations