126998RESERVE NOTICE12/05/2025 02:03:00 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1030 hrs to 1230 hrs 15/05/2025.
The forecast capacity reserve requirement is 438 MW.
The minimum capacity reserve available is 401 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
126930INTER-REGIONAL TRANSFER07/05/2025 02:33:00 PM

Inter-regional transfer limit variation - Newcastle - Eraring (90) 330 kV line - NSW region - 07/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Newcastle - Eraring (90) 330 kV line - NSW region - 07/05/2025

A planned outage of Newcastle - Eraring (90) 330 kV line in the NSW region was scheduled from 0700 hrs 07/05/2025 to 1700 hrs 10/05/2025.

The outage has been completed and Newcastle - Eraring (90) 330 kV line returned to service at 1335 hrs 07/05/2025

Constraint set(s) revoked: N-ERNC_90

Manager NEM Real Time Operations
     
126903INTER-REGIONAL TRANSFER06/05/2025 12:59:40 PM

Inter-regional transfer limit variation - South East - Tailem Bend No. 2 275 kV Line - SA region - 06/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East - Tailem Bend No. 2 275 kV Line - SA region - 06/05/2025

At 1300 hrs 06/05/2025 there was a short notice outage of South East - Tailem Bend No. 2 275 kV Line .

The following constraint set(s) invoked at 1300 hrs 06/05/2025
S-TBSE

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126871INTER-REGIONAL TRANSFER05/05/2025 01:52:26 PM

Inter-regional transfer limit variation - Greenbank - Mudgeeraba No. 836 275 kV Line - QLD region - 05/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank - Mudgeeraba No. 836 275 kV Line - QLD region - 05/05/2025

At 1336 hrs 05/05/2025 there was an unplanned outage of Greenbank - Mudgeeraba No. 836 275 kV Line.

The following constraint set(s) invoked at 1340 hrs 05/05/2025
Q-GBMU_835_836

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126853INTER-REGIONAL TRANSFER03/05/2025 04:11:50 PM

Inter-regional transfer limit variation - South Morang - Thomastown No 2 220 kV Line - VIC region - 03/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -South Morang - Thomastown No 2 220 kV Line - VIC region - 03/05/2025

A planned outage of South Morang - Thomastown No 2 220 kV Line in the VIC region was scheduled from 0629 hrs 03/05/2025 to 1830 hrs 03/05/2025.

The outage has been completed and South Morang - Thomastown No 2 220 kV Line returned to service at 1615 hrs 03/05/2025

Constraint set(s) revoked: V-SMTT2

Manager NEM Real Time Operations
     
126812INTER-REGIONAL TRANSFER30/04/2025 04:31:48 PM

Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025

A planned outage of Red Cliffs - Buronga X1 220kV Line in the NSW region was scheduled from 0700 hrs 27/04/2025 to 1700 hrs 02/05/2025.

The outage has been completed and Red Cliffs - Buronga X1 220kV Line returned to service at 1625 hrs 30/04/2025

Constraint set(s) revoked: I-BURC_X1

Manager NEM Real Time Operations
     
126783INTER-REGIONAL TRANSFER29/04/2025 04:51:17 PM

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line- NSW region - 29/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line - NSW region - 29/04/2025

A planned outage of Eraring - Kemps Creek 5A1 500 kV line in the NSW region was scheduled from 0730 hrs 28/04/2025 to 1600 hrs 02/05/2025.

The outage has been completed and Eraring - Kemps Creek 5A1 500 kV line returned to service at 1650 hrs 29/04/2025

Constraint set revoked: N-ERKC_ONE

Manager NEM Real Time Operations
     
126740INTER-REGIONAL TRANSFER26/04/2025 11:57:04 AM

Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025

At 1140 hrs 26/04/2025 there was a short notice outage of Griffith - Yanco 99J 132 kV Line.

The following constraint set(s) invoked at 1140 hrs 26/04/2025
N-GFYC-99J-C

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126600POWER SYSTEM EVENTS20/04/2025 06:23:59 AM

Update - Non-credible contingency event - NSW region - 19/04/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 19/04/2025

Refer AEMO Electricity Market Notice 126598

At 0617 hrs the Uralla - New England Solar Farm No.1 330/33 kV Transformer and New England No.2 Solar Farm was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     