Market Notices

127003RESERVE NOTICE12/05/2025 04:00:44 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 126998 has been updated at 1500 hrs 12/05/2025 to the following:

From 1430 hrs to 1500 hrs 15/05/2025.
The forecast capacity reserve requirement is 461 MW.
The minimum capacity reserve available is 453 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
126998RESERVE NOTICE12/05/2025 02:03:00 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1030 hrs to 1230 hrs 15/05/2025.
The forecast capacity reserve requirement is 438 MW.
The minimum capacity reserve available is 401 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
126930INTER-REGIONAL TRANSFER07/05/2025 02:33:00 PM

Inter-regional transfer limit variation - Newcastle - Eraring (90) 330 kV line - NSW region - 07/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Newcastle - Eraring (90) 330 kV line - NSW region - 07/05/2025

A planned outage of Newcastle - Eraring (90) 330 kV line in the NSW region was scheduled from 0700 hrs 07/05/2025 to 1700 hrs 10/05/2025.

The outage has been completed and Newcastle - Eraring (90) 330 kV line returned to service at 1335 hrs 07/05/2025

Constraint set(s) revoked: N-ERNC_90

Manager NEM Real Time Operations
     
126903INTER-REGIONAL TRANSFER06/05/2025 12:59:40 PM

Inter-regional transfer limit variation - South East - Tailem Bend No. 2 275 kV Line - SA region - 06/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East - Tailem Bend No. 2 275 kV Line - SA region - 06/05/2025

At 1300 hrs 06/05/2025 there was a short notice outage of South East - Tailem Bend No. 2 275 kV Line .

The following constraint set(s) invoked at 1300 hrs 06/05/2025
S-TBSE

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126871INTER-REGIONAL TRANSFER05/05/2025 01:52:26 PM

Inter-regional transfer limit variation - Greenbank - Mudgeeraba No. 836 275 kV Line - QLD region - 05/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank - Mudgeeraba No. 836 275 kV Line - QLD region - 05/05/2025

At 1336 hrs 05/05/2025 there was an unplanned outage of Greenbank - Mudgeeraba No. 836 275 kV Line.

The following constraint set(s) invoked at 1340 hrs 05/05/2025
Q-GBMU_835_836

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126853INTER-REGIONAL TRANSFER03/05/2025 04:11:50 PM

Inter-regional transfer limit variation - South Morang - Thomastown No 2 220 kV Line - VIC region - 03/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -South Morang - Thomastown No 2 220 kV Line - VIC region - 03/05/2025

A planned outage of South Morang - Thomastown No 2 220 kV Line in the VIC region was scheduled from 0629 hrs 03/05/2025 to 1830 hrs 03/05/2025.

The outage has been completed and South Morang - Thomastown No 2 220 kV Line returned to service at 1615 hrs 03/05/2025

Constraint set(s) revoked: V-SMTT2

Manager NEM Real Time Operations
     
126812INTER-REGIONAL TRANSFER30/04/2025 04:31:48 PM

Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025

A planned outage of Red Cliffs - Buronga X1 220kV Line in the NSW region was scheduled from 0700 hrs 27/04/2025 to 1700 hrs 02/05/2025.

The outage has been completed and Red Cliffs - Buronga X1 220kV Line returned to service at 1625 hrs 30/04/2025

Constraint set(s) revoked: I-BURC_X1

Manager NEM Real Time Operations
     
126786CONSTRAINTS29/04/2025 05:43:58 PM

Updated Victorian system normal voltage stability limit for the south-west Victoria

AEMO ELECTRICITY MARKET NOTICE

Refer to Market Notice 101368

AEMO has completed a review of the system normal voltage stability limit in the south-west Victoria as a result of Mortlake terminal station cut-in on the Haunted Gully to Tarrone 500 kV line.

The revised limit is increased by 100 MW on the cut-set from Haunted Gully to Moorabool and Mortlake to Moorabool 500 kV lines for flow towards Moorabool.

Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

The revised limit has been implemented at 1201 hrs on Tuesday 29th April 2025, by updating V^^V_NIL_SWVIC.

For further details on this constraint equation please contact terry.liu@aemo.com.au

Terry Liu
AEMO Operations
     
126783INTER-REGIONAL TRANSFER29/04/2025 04:51:17 PM

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line- NSW region - 29/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line - NSW region - 29/04/2025

A planned outage of Eraring - Kemps Creek 5A1 500 kV line in the NSW region was scheduled from 0730 hrs 28/04/2025 to 1600 hrs 02/05/2025.

The outage has been completed and Eraring - Kemps Creek 5A1 500 kV line returned to service at 1650 hrs 29/04/2025

Constraint set revoked: N-ERKC_ONE

Manager NEM Real Time Operations
     