Filter by category
Filter by Date
Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Duration: 05/05/2025 20:59 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Duration: 05/05/2025 20:31 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Palmerston - Hadspen 3 & 4 110kV and
Duration: 05/05/2025 20:27 until further notice
Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Sheffield - George Town No1 220kV line and Sheffield - George Town No2 220kV line in TAS due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS
Lines: Sheffield - George Town No1 220kV line and Sheffield - George Town No2 220kV line
Duration:19:30 hrs 05/05/2025 until further notice
Constraint set(s) invoked:
T-GTSH_N-2
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Ulverstone - Emu Bay 110kV line and Sheffield - Paloona - Ulverstone 1 & 2 110kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Ulverstone - Emu Bay 110kV and Sheffield - Paloona - Ulverstone 1 & 2 110kV
Duration: 05/05/2025 19:12 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Gordon - Chapel St No 1 220kV line and Gordon - Chapel St No 2 220kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Gordon - Chapel St No 1 220kV and Gordon - Chapel St No 2 220kV
Duration: 05/05/2025 19:12 until further notice
Constraint set(s) invoked:
F-T-CSGO Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-CSGO_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Burnie - Port Latta - Smithton 1 110kV line and Burnie - Port Latta - Smithton 2 110kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Burnie - Port Latta - Smithton 1 110kV and Burnie - Port Latta - Smithton 2 110kV
Duration: 05/05/2025 18:39 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202505051830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 05 May 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 5 May 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 5 May 2025.
Refer to market notice: 126877
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 5 May 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202505051705_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 05 May 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 5 May 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 5 May 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1705 hrs on 5 May 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.