STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 17/06/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127577 is cancelled at 1200 hrs 16/06/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
[EventId:202506161100_review] Prices for interval 16-Jun-2025 11:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1055 hrs on 16 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jun-2025 11:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506161055_review] Prices for interval 16-Jun-2025 10:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1050 hrs on 16 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jun-2025 10:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506161050_review] Prices for interval 16-Jun-2025 10:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1045 hrs on 16 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jun-2025 10:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506161045_review] Prices for interval 16-Jun-2025 10:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1040 hrs on 16 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jun-2025 10:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506161040_review] Prices for interval 16-Jun-2025 10:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 16 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jun-2025 10:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506161035_review] Prices for interval 16-Jun-2025 10:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 16 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jun-2025 10:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 17/06/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127576 is cancelled at 1000 hrs 16/06/2025.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 17/06/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127561 has been updated at 0900 hrs 16/06/2025 to the following:
1. From 1000 hrs to 1130 hrs 17/06/2025.
The forecast capacity reserve requirement is 706 MW.
The minimum capacity reserve available is 489 MW.
2. From 1400 hrs to 1430 hrs 17/06/2025.
The forecast capacity reserve requirement is 697 MW.
The minimum capacity reserve available is 514 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations