Inter-regional transfer limit variation - Newcastle - Eraring (90) 330 kV line - NSW region - 07/05/2025
Inter-regional transfer limit variation - Newcastle - Eraring (90) 330 kV line - NSW region - 07/05/2025
A planned outage of Newcastle - Eraring (90) 330 kV line in the NSW region was scheduled from 0700 hrs 07/05/2025 to 1700 hrs 10/05/2025.
The outage has been completed and Newcastle - Eraring (90) 330 kV line returned to service at 1335 hrs 07/05/2025
Constraint set(s) revoked: N-ERNC_90
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South East - Tailem Bend No. 2 275 kV Line - SA region - 06/05/2025
Inter-regional transfer limit variation - South East - Tailem Bend No. 2 275 kV Line - SA region - 06/05/2025
At 1300 hrs 06/05/2025 there was a short notice outage of South East - Tailem Bend No. 2 275 kV Line .
The following constraint set(s) invoked at 1300 hrs 06/05/2025
S-TBSE
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank - Mudgeeraba No. 836 275 kV Line - QLD region - 05/05/2025
Inter-regional transfer limit variation - Greenbank - Mudgeeraba No. 836 275 kV Line - QLD region - 05/05/2025
At 1336 hrs 05/05/2025 there was an unplanned outage of Greenbank - Mudgeeraba No. 836 275 kV Line.
The following constraint set(s) invoked at 1340 hrs 05/05/2025
Q-GBMU_835_836
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Morang - Thomastown No 2 220 kV Line - VIC region - 03/05/2025
Inter-regional transfer limit variation -South Morang - Thomastown No 2 220 kV Line - VIC region - 03/05/2025
A planned outage of South Morang - Thomastown No 2 220 kV Line in the VIC region was scheduled from 0629 hrs 03/05/2025 to 1830 hrs 03/05/2025.
The outage has been completed and South Morang - Thomastown No 2 220 kV Line returned to service at 1615 hrs 03/05/2025
Constraint set(s) revoked: V-SMTT2
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025
Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025
A planned outage of Red Cliffs - Buronga X1 220kV Line in the NSW region was scheduled from 0700 hrs 27/04/2025 to 1700 hrs 02/05/2025.
The outage has been completed and Red Cliffs - Buronga X1 220kV Line returned to service at 1625 hrs 30/04/2025
Constraint set(s) revoked: I-BURC_X1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line- NSW region - 29/04/2025
Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line - NSW region - 29/04/2025
A planned outage of Eraring - Kemps Creek 5A1 500 kV line in the NSW region was scheduled from 0730 hrs 28/04/2025 to 1600 hrs 02/05/2025.
The outage has been completed and Eraring - Kemps Creek 5A1 500 kV line returned to service at 1650 hrs 29/04/2025
Constraint set revoked: N-ERKC_ONE
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025
Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025
At 1140 hrs 26/04/2025 there was a short notice outage of Griffith - Yanco 99J 132 kV Line.
The following constraint set(s) invoked at 1140 hrs 26/04/2025
N-GFYC-99J-C
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank - Molendinar 8825 275kV line - QLD region - 16/04/2025
Inter-regional transfer limit variation - Greenbank - Molendinar 8825 275kV line - QLD region - 16/04/2025
At 2110 hrs 16/04/2025 there was an unplanned outage of Greenbank - Molendinar 8825 275kV line.
The following constraint set(s) invoked at 2120 hrs 16/04/2025
Q-GBMO_8824_8825
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 14/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 14/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126559 is cancelled at 1811 hrs 14/04/2025.