Market Notices

127482RESERVE NOTICE08/06/2025 07:25:26 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1800 hrs 11/06/2025 to 1900 hrs 11/06/2025.
The forecast capacity reserve requirement is 881 MW.
The minimum capacity reserve available is 856 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
127481RESERVE NOTICE08/06/2025 07:24:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 127480 has been updated to the following:

[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 654 MW.
The minimum capacity reserve available is 608 MW.

[2.] From 1830 hrs 10/06/2025 to 1930 hrs 10/06/2025.
The forecast capacity reserve requirement is 905 MW.
The minimum capacity reserve available is 895 MW.

AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
127480RESERVE NOTICE08/06/2025 06:18:03 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127477 has been updated at 1815 hrs to the following:

[1.] From 0630 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 657 MW.
The minimum capacity reserve available is 619 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127477RESERVE NOTICE08/06/2025 02:24:30 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127447 has been updated at 1415 hrs to the following:

[1.] From 0600 hrs 10/06/2025 to 0700 hrs 10/06/2025.
The forecast capacity reserve requirement is 728 MW.
The minimum capacity reserve available is 612 MW.

[2.] From 1830 hrs 10/06/2025 to 1930 hrs 10/06/2025.
The forecast capacity reserve requirement is 919 MW.
The minimum capacity reserve available is 900 MW.
AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127447RESERVE NOTICE07/06/2025 11:59:12 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127435 has been updated at 1145hrs to the following:

From 0600 hrs 10/06/2025 to 0730 hrs 10/06/2025.
The forecast capacity reserve requirement is 832 MW.
The minimum capacity reserve available is 585 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127435RESERVE NOTICE07/06/2025 07:29:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 0630 hrs to 0700 hrs 10/06/2025:
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 585 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127406POWER SYSTEM EVENTS06/06/2025 08:43:55 AM

Non-credible contingency event - VIC region - 06/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 06/06/2025

At 0830 hrs the Wodonga No 2 330kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
127304POWER SYSTEM EVENTS27/05/2025 12:30:40 PM

Update - Non-credible contingency event - NSW region - 07/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 07/03/2025

Refer AEMO Electricity Market Notice 125536

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will no longer reclassify this event as a credible contingency event.

Region: NSW

Elements:
- Lismore132 - Mullumbimby 9U6 132kV Line
- Lismore132 - Mullumbimby 9U7 132kV Line
- Ewingsdale - Mullumbimby 9G5 132kV Line

Duration: 1730 hrs 11/03/2025 until 1230 hrs 27/05/2025

Constraint set(s) invoked: NONE

Manager NEM Real Time Operations
     
127008RESERVE NOTICE12/05/2025 08:39:09 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127006 is cancelled at 2035 hrs 12/05/2025

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm