Market Notices

127449INTER-REGIONAL TRANSFER07/06/2025 12:06:39 PM

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

Refer AEMO Electricity Market Notice 127439

AEMO has been notified that the controls to vary Murraylink output are now available.

Constraint set I-CTRL_ISSUE_ML revoked at 1150 hrs.

Manager NEM Real Time Operations
     
127448INTER-REGIONAL TRANSFER07/06/2025 12:06:34 PM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 127438

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 1150 hrs.

Manager NEM Real Time Operations
     
127447RESERVE NOTICE07/06/2025 11:59:12 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No.127435 has been updated at 1145hrs to the following:

From 0600 hrs 10/06/2025 to 0730 hrs 10/06/2025.
The forecast capacity reserve requirement is 832 MW.
The minimum capacity reserve available is 585 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127439INTER-REGIONAL TRANSFER07/06/2025 09:21:20 AM

Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_ML invoked from 0920 hrs.

The constraint set contains equations with the following interconnector on the LHS:

V-S-MNSP1


Manager NEM Real Time Operations
     
127438INTER-REGIONAL TRANSFER07/06/2025 08:58:31 AM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 0855 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations
     
127435RESERVE NOTICE07/06/2025 07:29:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 0630 hrs to 0700 hrs 10/06/2025:
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 585 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127431PRICES UNCHANGED06/06/2025 06:00:21 PM

[EventId:202506061740_confirmed] Prices for interval 06-Jun-2025 17:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025

PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:40.

In accordance with Market Notice 127420 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127430PRICES UNCHANGED06/06/2025 06:00:21 PM

[EventId:202506061800_confirmed] Prices for interval 06-Jun-2025 18:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025

PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 18:00.

In accordance with Market Notice 127425 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127429PRICES UNCHANGED06/06/2025 06:00:21 PM

[EventId:202506061755_confirmed] Prices for interval 06-Jun-2025 17:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 6 June 2025

PRICES ARE NOW CONFIRMED for trading interval 06-Jun-2025 17:55.

In accordance with Market Notice 127424 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     