Market Notices

126791PRICES SUBJECT TO REVIEW30/04/2025 10:45:26 AM

[EventId:202504301050_review] Prices for interval 30-Apr-2025 10:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1045 hrs on 30 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126790PRICES SUBJECT TO REVIEW30/04/2025 10:40:19 AM

[EventId:202504301045_review] Prices for interval 30-Apr-2025 10:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1040 hrs on 30 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126789PRICES SUBJECT TO REVIEW30/04/2025 10:35:23 AM

[EventId:202504301040_review] Prices for interval 30-Apr-2025 10:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 30 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 30-Apr-2025 10:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126788MARKET SYSTEMS30/04/2025 09:18:02 AM

CHG0102918:Network Change Impacting Norwest and Brisbane Control Room Phone Network

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Network Change Impacting Norwest and Brisbane Control Room Phone Network
Change Start Date & Time: 01/05/2025 11:00:00
Change End Date & Time: 01/05/2025 16:00:00
Outage Start Date & Time: 01/05/2025 12:00:00
Outage End Date & Time: 01/05/2025 15:00:00
Environment: Production
Participant Impact and Requirements: Possibility of experiencing 2 x 30 seconds outages to Norwest and Brisbane Control Room phone networks on 1st May between 12 pm and 2 pm. You are hereby advised to maintain status quo and continue to reach out the Control rooms as you would normally do and only call Norwest on 02 8884 5291 or 02 8884 5292 and Brisbane on 0733473291 or 0733473292 if you have any trouble at all reaching them on their regular operating lines.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
126787RECLASSIFY CONTINGENCY29/04/2025 09:39:51 PM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 29/04/2025 21:39

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 126774

Auto-generated on behalf of Manager NEM Real Time Operations
     
126786CONSTRAINTS29/04/2025 05:43:58 PM

Updated Victorian system normal voltage stability limit for the south-west Victoria

AEMO ELECTRICITY MARKET NOTICE

Refer to Market Notice 101368

AEMO has completed a review of the system normal voltage stability limit in the south-west Victoria as a result of Mortlake terminal station cut-in on the Haunted Gully to Tarrone 500 kV line.

The revised limit is increased by 100 MW on the cut-set from Haunted Gully to Moorabool and Mortlake to Moorabool 500 kV lines for flow towards Moorabool.

Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

The revised limit has been implemented at 1201 hrs on Tuesday 29th April 2025, by updating V^^V_NIL_SWVIC.

For further details on this constraint equation please contact terry.liu@aemo.com.au

Terry Liu
AEMO Operations
     
126785RECLASSIFY CONTINGENCY29/04/2025 05:29:53 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 29/04/2025 17:29

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 126778

Auto-generated on behalf of Manager NEM Real Time Operations
     
126783INTER-REGIONAL TRANSFER29/04/2025 04:51:17 PM

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line- NSW region - 29/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line - NSW region - 29/04/2025

A planned outage of Eraring - Kemps Creek 5A1 500 kV line in the NSW region was scheduled from 0730 hrs 28/04/2025 to 1600 hrs 02/05/2025.

The outage has been completed and Eraring - Kemps Creek 5A1 500 kV line returned to service at 1650 hrs 29/04/2025

Constraint set revoked: N-ERKC_ONE

Manager NEM Real Time Operations
     
126782MARKET INTERVENTION29/04/2025 03:58:11 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126779

In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 29/04/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 30/04/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1830 hrs 30/04/2025.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm