Market Notices

70966RECLASSIFY CONTINGENCY06/11/2019 05:18:55 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 06/11/2019 17:18

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 70963

Auto-generated on behalf of Manager NEM Real Time Operations
70965RECLASSIFY CONTINGENCY06/11/2019 04:38:55 PM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Duration: 06/11/2019 16:38 until further notice

Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
70964RECLASSIFY CONTINGENCY06/11/2019 04:16:50 PM

Reclassification of a Non-Credible Contingency Event: Farrell-Sheffield No.1 220 kV line and Farrell-Sheffield No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-Sheffield No.1 220 kV and Farrell-Sheffield No.2 220 kV

Duration: 06/11/2019 16:16 until further notice

Constraint set(s) invoked:
F-WESTCOAST_REG_0 Constraint set contains the following interconnector(s) on the left hand side:
NONE
T-FASH_N-2_CP4_S4 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
70963RECLASSIFY CONTINGENCY06/11/2019 04:16:50 PM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 06/11/2019 16:16 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
70962RECLASSIFY CONTINGENCY06/11/2019 03:31:35 PM

Reclassification of a Non-Credible Contingency Event: Sheffield - Wesley Vale 110kV line and Sheffield - Devonport 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Sheffield - Wesley Vale 110kV and Sheffield - Devonport 110kV

Duration: 06/11/2019 15:30 until further notice

Constraint set(s) invoked:
NONE

Manager NEM Real Time Operation
70961NON-CONFORMANCE06/11/2019 02:55:19 PM

NON-CONFORMANCE Region NSW1 Wednesday, 6 November 2019

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 6 November 2019

AEMO declared a schedule generating unit non-conforming

Unit: MP1
Duration: 06/11/2019 14:40 to 06/11/2019 14:55
Amount: 13 MW
Constraint: NC-N_MP1

Auto-generated on behalf of Manager NEM Real Time Operations
70960RECLASSIFY CONTINGENCY06/11/2019 02:52:40 PM

Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Duration: 06/11/2019 14:52 until further notice

Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
70959MARKET INTERVENTION06/11/2019 04:24:30 PM

Update - AEMO Intervention Event - Intervention price dispatch intervals - 05/11/2019

AEMO ELECTRICITY MARKET NOTICE

Update - AEMO Intervention Event - Intervention price dispatch intervals

Refer AEMO Electricity Market Notice no. 70952 and 70953

The AEMO Intervention Event commenced in the 1705 hrs dispatch interval on 05/11/2019 and is now forecast to apply until 1430 hrs 08/11/2019.

Manager NEM Real Time Operations
70955INTER-REGIONAL TRANSFER06/11/2019 09:30:58 AM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 2 Leg of Directlink .

The following constraint set was invoked at 0930 hrs 06/11/2019.

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations