PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/10/2019
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 70792 is cancelled at 1100 hrs 30/10/2019.
Manager NEM Real Time Operations
CHG0056591 : STTM Pre-Production Database Refresh
Change Number: CHG0056591
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: STTM - Scheduling & Dispatch
Change Title: STTM Pre-Production Database Refresh
Change Start Date & Time: 01/11/2019 09:00:00 AEST
Change End Date & Time: 01/11/2019 14:00:00 AEST
Outage Start Date & Time: 01/11/2019 09:00:00 AEST
Outage End Date & Time: 01/11/2019 14:00:00 AEST
Change Description:
Gas STTM Pre-Production will have an outage for maintenance
Environment: Pre-Production
Participant Impact and Requirements:
Gas STTM Pre-Production systems (including SWEX, SWEXIE and MIS for participants) will be unavailable for the duration of the outage. Internal STTM applications and access will also be unavailable during the works.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - Armidale-Koolkhan 966 132 kV Line - NSW region - 30/10/2019
At 1036 hrs 30/10/2019 there was a short notice outage of Armidale-Koolkhan 966 132 kV Line.
The following constraint set invoked at 1040 hrs 30/10/2019
N-X_ARKK_CH_CB892A
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1 - QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0056629: Apply Change to address performance issues on the EMMS FTP File Server
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Expedited
Service/ Component: EMMS - Data Interchange
Change Title: Apply Change to address performance issues on the EMMS FTP File Server
Change Start Date & Time: 30/10/2019 08:00:00 AEST
Change End Date & Time: 30/10/2019 13:30:00 AEST
Outage Start Date & Time: 30/10/2019 13:27:00 AEST
Outage End Date & Time: 30/10/2019 13:28:00 AEST
Change Description:
Preventative maintenance to proactively address performance issues observed.
Environment: Production
Participant Impact and Requirements:
Participants will notice a brief disconnection and reconnection to the FTP interface of the server during the change window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/10/2019
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 30/10/2019 to 1800 hrs 30/08/2019.
The forecast capacity reserve requirement is 1554 MW.
The minimum capacity reserve available is 1506 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/10/2019
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 70790 is cancelled at 0800 hrs 30/10/2019.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/10/2019
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.70789 has been updated at 0730 hrs to the following:
From 1130 hrs 30/10/2019 to 1200 hrs 30/10/2019
The contingency forecast capacity reserve requirement is 1320 MW.
The minimum capacity reserve available is 1225 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/10/2019
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.70781 has been updated at 0030 hrs to the following:
From 0900 hrs 30/10/2019 to 1230 hrs 30/10/2019
The contingency forecast capacity reserve requirementd is 1320 MW.
The minimum capacity reserve available is 813 MW.
From 1530 hrs 30/10/2019 to 1800 hrs 30/10/2019
The contingency forecast capacity reserve requirementd is 1536 MW.
The minimum capacity reserve available is 1421 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 31/10/2019
AEMO ELECTRICITY MARKET NOTICE
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 70784 is cancelled at 0030 hrs 30/10/2019.
[No LOR2 condition is currently forecast in the STPASA period.]
Manager NEM Real Time Operations