Filter by category
Filter by Date
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1900 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 693 MW
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 11/06/2025
Update - Non-credible contingency event - QLD region - 11/06/2025
Refer AEMO Electricity Market Notice 127500
At 1050 hrs the Belmont - Loganlea 829 275 kV line was returned to service and previously (11/06/25) the Belmont (H3) No. 1 275 kV bus had returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 11/06/2025
Update - Non-credible contingency event - QLD region - 11/06/2025
Refer AEMO Electricity Market Notice 127499
At 1713 hrs the Belmont (H3) No.1 275 kV bus and Loganlea - Belmont (829) 275 kV line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 11/06/2025
Non-credible contingency event - QLD region - 11/06/2025
At 1713 hrs the Belmont (H3) No.1 275 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127419
Manager NEM Real Time Operations
Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127418
Manager NEM Real Time Operations
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 127450 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 2345 hrs 7/06/2025
Constraint set(s) revoked:
I-VS_250
Manager NEM Real Time Operations
Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely severe weather in the SA region.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.
AEMO has taken the following action to maintain power system security at 1250 hrs 07/06/2025.
Constraint set invoked:
I-VS_250
Duration: 1255 hrs until further notice
Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Cancellation time: 07/06/2025 09:44
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 127434
Auto-generated on behalf of Manager NEM Real Time Operations