Market Notices

115296INTER-REGIONAL TRANSFER28/02/2024 03:25:40 PM

Inter-regional transfer limit variation - 275kV South Pine SVC - QLD region - 28/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -275kV South Pine SVC - QLD region - 28/02/2024

At 1425 hrs 28/02/2024 there was an unplanned outage of 275kV South Pine SVC.

Constraint set Q-SP_VC invoked from 1435 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1
NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115256INTER-REGIONAL TRANSFER28/02/2024 11:02:16 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/02/2024

In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_54F10C1F from 1035 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S_MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
115209SETTLEMENTS RESIDUE27/02/2024 01:30:24 PM

[EventId:202402271330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 February 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 27 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 February 2024.

Refer to market notice: 115207

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 27 February 2024.

This is an AEMO autogenerated Market Notice.
115207SETTLEMENTS RESIDUE27/02/2024 12:05:23 PM

[EventId:202402271205_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 February 2024 12:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1205 hrs on 27 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1205 hrs on 27 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115177SETTLEMENTS RESIDUE26/02/2024 07:01:40 PM

[EventId:202402261900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 26 February 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 26 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 February 2024.

Refer to market notice: 115162

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 26 February 2024.

This is an AEMO autogenerated Market Notice.
115174SETTLEMENTS RESIDUE26/02/2024 06:50:26 PM

[EventId:202402261850_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 26 February 2024 18:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1850 hrs on 26 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 26 February 2024.

Refer to market notice: 115163

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1850 hrs on 26 February 2024.

This is an AEMO autogenerated Market Notice.
115163SETTLEMENTS RESIDUE26/02/2024 05:47:46 PM

[EventId:202402261745_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 26 February 2024 17:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1746 hrs on 26 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 26 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1745 hrs on 26 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115162SETTLEMENTS RESIDUE26/02/2024 05:48:37 PM

[EventId:202402261745_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 26 February 2024 17:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1746 hrs on 26 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1745 hrs on 26 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115149SETTLEMENTS RESIDUE26/02/2024 03:00:22 PM

[EventId:202402261500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 26 February 2024 15:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 26 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 February 2024.

Refer to market notice: 115133

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 26 February 2024.

This is an AEMO autogenerated Market Notice.