Reclassification of a Non-Credible Contingency Event: Farrell - Sheffield No. 1 and 2 220kV Lines in TAS due to Bushfire.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Bushfire. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS
Lines: Farrell - Sheffield No. 1 and 2 220kV Lines
Duration:12:50 hrs 22/04/2024 until further notice
Constraint set(s) invoked:
T-NIL_WCP_CLOSE
F-FASH_N-2_CP4_SB
Manager NEM Real Time Operations
[EventId:202404220900_review] Prices for interval 22-Apr-2024 09:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0855 hrs on 22 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Apr-2024 09:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404220855_review] Prices for interval 22-Apr-2024 08:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0850 hrs on 22 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Apr-2024 08:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404220850_review] Prices for interval 22-Apr-2024 08:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0845 hrs on 22 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Apr-2024 08:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404220845_review] Prices for interval 22-Apr-2024 08:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0840 hrs on 22 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Apr-2024 08:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404220840_review] Prices for interval 22-Apr-2024 08:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 22 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Apr-2024 08:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404220835_review] Prices for interval 22-Apr-2024 08:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0830 hrs on 22 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Apr-2024 08:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404220830_review] Prices for interval 22-Apr-2024 08:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 0825 hrs on 22 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Apr-2024 08:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404220825_review] Prices for interval 22-Apr-2024 08:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 0820 hrs on 22 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Apr-2024 08:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs