Market Notices

96682RECALL GEN CAPACITY31/05/2022 03:22:18 PM

Request for Generator Recall Information for 02/06/2022 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 96666.

Please provide Generator Recall Information for 02/06/2022 by 1400 hrs AEST on 01/06/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
96681RECALL GEN CAPACITY31/05/2022 03:23:06 PM

Request for Generator Recall Information for 02/06/2022 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 96668.

Please provide Generator Recall Information for 02/06/2022 by 1400 hrs AEST on 01/06/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
94226RECALL GEN CAPACITY30/01/2022 06:50:14 PM

Request for Generator Recall Information for the period for 02/02/2022 for OLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 94225

Please provide Generator Recall Information for 02/02/2022 by 1200 hrs EST on 31/01/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

Manager NEM Real Time Operations
94211RECALL GEN CAPACITY30/01/2022 11:15:30 AM

Update - Request for Generator Recall Information for the period for 01/02/2022 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Correction to external reference in AEMO Electricity Market Notice 94209. It should read Qld.

Refer to AEMO Electricity Market Notice 94205

Please provide Generator Recall Information for 01/02/2022 by 1200 hrs EST on 31/01/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

Manager NEM Real Time Operations
94210RECALL GEN CAPACITY30/01/2022 10:54:33 AM

Request for Generator Recall Information for the period for 01/02/2022 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 94208

Please provide Generator Recall Information for 01/02/2022 by 1200 hrs EST on 31/01/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

Manager NEM Real Time Operations
94209RECALL GEN CAPACITY30/01/2022 10:53:37 AM

Request for Generator Recall Information for the period for 01/02/2022 for OLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 94205

Please provide Generator Recall Information for 01/02/2022 by 1200 hrs EST on 31/01/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

Manager NEM Real Time Operations
94207RECALL GEN CAPACITY30/01/2022 08:57:36 AM

Cancellation of the Request for Generator Recall Information for 02/02/2022 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer the AEMO Electricity Market Notice No.94190

Capacity reserves in QLD region for 02/02/2022 have increased and the LOR2 condition no longer exists for this day.

Hence AEMO withdraws the request for provding Generator Recall Information for QLD region for 02/02/2022.


Manager NEM Real Time Operations
94190RECALL GEN CAPACITY29/01/2022 05:50:05 PM

Request for Generator Recall Information for the period for 02/02/2022 for OLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 94189

Please provide Generator Recall Information for 02/02/2022 by 1200 hrs EST on 31/01/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

Manager NEM Real Time Operations
94175RECALL GEN CAPACITY29/01/2022 09:43:03 AM

Cancellation of the Request for Generator Recall Information for 02/02/2022 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer the AEMO Electricity Market Notice No.94080

Capacity reserves in QLD region for 02/02/2022 have increased and the LOR2 condition no longer exists for this day.

Hence AEMO withdraws the request for provding Generator Recall Information for QLD region for 02/02/2022.


Manager NEM Real Time Operations