96776PROTECTED EVENT04/06/2022 07:16:06 PM

Protected event advice - South Australia region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO has identified that the conditions of the following protected event will be met from the time specified in this notice.

Protected event: the loss of multiple transmission elements causing generation disconnection in the South Australia region during periods where destructive wind conditions are forecast by the Bureau of Meteorology.

Duration: 1915 hrs 04/06/2022 until further notice

AEMO will take action to manage the power system for the impact of the protected event.

Constraint set(s) invoked: I-VS_250

Manager NEM Real Time Operations
96682RECALL GEN CAPACITY31/05/2022 03:22:18 PM

Request for Generator Recall Information for 02/06/2022 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 96666.

Please provide Generator Recall Information for 02/06/2022 by 1400 hrs AEST on 01/06/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
96681RECALL GEN CAPACITY31/05/2022 03:23:06 PM

Request for Generator Recall Information for 02/06/2022 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 96668.

Please provide Generator Recall Information for 02/06/2022 by 1400 hrs AEST on 01/06/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
95169RESERVE NOTICE08/03/2022 07:32:53 PM

Cancellation of Actual (LOR2) in the QLD region - 08/03/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) in the QLD region - 08/03/2022

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No. 95166 is cancelled at 1930 hrs 08/03/2022.

Manager NEM Real Time Operations
95166RESERVE NOTICE08/03/2022 05:43:22 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/03/2022

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 08/03/2022

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.

The Actual LOR2 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 443 MW.
The minimum capacity reserve available is 314 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
94406RESERVE NOTICE01/02/2022 07:59:09 PM

Cancellation of Actual (LOR2) condition in the QLD region - 01/02/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the QLD region - 01/02/2022

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.94395 is cancelled at 2000 hrs 01/02/2022.

Manager NEM Real Time Operations
94395RESERVE NOTICE01/02/2022 05:38:32 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 01/02/2022

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 01/02/2022

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1700 hrs.

The forecast capacity reserve requirement is 443 MW.
The minimum capacity reserve available is 77 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
94226RECALL GEN CAPACITY30/01/2022 06:50:14 PM

Request for Generator Recall Information for the period for 02/02/2022 for OLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 94225

Please provide Generator Recall Information for 02/02/2022 by 1200 hrs EST on 31/01/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

Manager NEM Real Time Operations
94211RECALL GEN CAPACITY30/01/2022 11:15:30 AM

Update - Request for Generator Recall Information for the period for 01/02/2022 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Correction to external reference in AEMO Electricity Market Notice 94209. It should read Qld.

Refer to AEMO Electricity Market Notice 94205

Please provide Generator Recall Information for 01/02/2022 by 1200 hrs EST on 31/01/2022 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm