[EventId:201610030040_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 03 October 2016 00:40
Issued by Australian Energy Market Operator Ltd at 0040 hrs on 3 October 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 3 October 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0040 hrs on 3 October 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201610030030_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 03 October 2016 00:30
Issued by Australian Energy Market Operator Ltd at 0030 hrs on 3 October 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 3 October 2016.
Refer to market notice: 55125
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 0030 hrs on 3 October 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201610030010_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 03 October 2016 00:10
Issued by Australian Energy Market Operator Ltd at 0010 hrs on 3 October 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 3 October 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0010 hrs on 3 October 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201610022345_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 02 October 2016 23:45
Issued by Australian Energy Market Operator Ltd at 2345 hrs on 2 October 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 2 October 2016.
Refer to market notice: 55122
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 2345 hrs on 2 October 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201610022205_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 02 October 2016 22:05
Issued by Australian Energy Market Operator Ltd at 2205 hrs on 2 October 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 2 October 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 2205 hrs on 2 October 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201610021800_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 02 October 2016 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 2 October 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 2 October 2016.
Refer to market notice: 55117
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1800 hrs on 2 October 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201610021735_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 02 October 2016 17:35
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 2 October 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 2 October 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1735 hrs on 2 October 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201610021720_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 02 October 2016 17:20
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 2 October 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 2 October 2016.
Refer to market notice: 55115
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1720 hrs on 2 October 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201610021630_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 02 October 2016 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 2 October 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 2 October 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1630 hrs on 2 October 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.