Updates to Victorian system normal stability constraint equations
The Victorian system normal constraint equations that determine Victorian export limits based on transient stability and voltage stability at Heywood for Victoria to South Australia flows will be updated to a revised formulation on 25 July 2016 after 1330 hrs. This revised formulation models the effects of higher flows on Victoria to SA on Heywood and the new series capacitors at Black Range.
The changes are to the following constraint equations :
V::N_NIL_V1
V::N_NIL_V2
V::N_NIL_Q1
V::N_NIL_Q2
V::N_NIL_S1
V::N_NIL_S2
V::N_NIL_SD
V^S_HYCP
Ben Blake
AEMO Operations
[EventId:201607131130_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 13 July 2016 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 13 July 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 13 July 2016.
Refer to market notice: 54468
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1130 hrs on 13 July 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201607131030_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 13 July 2016 10:30
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 13 July 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 13 July 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1030 hrs on 13 July 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201607131000_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 13 July 2016 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 13 July 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 13 July 2016.
Refer to market notice: 54466
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1000 hrs on 13 July 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201607130900_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 13 July 2016 09:00
Issued by Australian Energy Market Operator Ltd at 0900 hrs on 13 July 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 13 July 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 0900 hrs on 13 July 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201607121900_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 12 July 2016 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 12 July 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 12 July 2016.
Refer to market notice: 54455
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1900 hrs on 12 July 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201607121800_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 12 July 2016 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 12 July 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 12 July 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1800 hrs on 12 July 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201607121630_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 12 July 2016 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 12 July 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 12 July 2016.
Refer to market notice: 54442
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1630 hrs on 12 July 2016.
This is an AEMO autogenerated Market Notice.
[EventId:201607121505_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 12 July 2016 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 12 July 2016
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 12 July 2016.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1505 hrs on 12 July 2016.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.