114959NON-CONFORMANCE22/02/2024 03:00:18 PM

NON-CONFORMANCE Region SA1 Thursday, 22 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 22 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 22/02/2024 14:55 to 22/02/2024 15:00
Amount: 12 MW
Constraint: NC-S_HORNSDPR_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
114943MARKET SYSTEMS22/02/2024 10:51:39 AM

CHG0085807 | Pre-Production | MSATS - eMDM Pre-Production Maintenance AKS v1.27 upgrade

Change Number: CHG0085807
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: MSATS - eMDM Pre-Production Maintenance AKS v1.27 upgrade
Change Start Date & Time: 26/02/2024 12:00:00 AEST
Change End Date & Time: 26/02/2024 19:00:00 AEST
Outage Start Date & Time: 26/02/2024 12:00:00 AEST
Outage End Date & Time: 26/02/2024 16:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
114937MARKET SYSTEMS22/02/2024 09:56:46 AM

CHG0085737 | Pre-Production | Pre-production EMMS database refresh

Change Number: CHG0085737
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Pre-production EMMS database refresh
Change Start Date & Time: 26/02/2024 08:00:00 AEST
Change End Date & Time: 17/03/2024 17:30:00 AEST
Outage Start Date & Time: 04/03/2024 08:00:00 AEST
Outage End Date & Time: 08/03/2024 19:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: The pre-production EMMS environment will be refreshed with production data (NEM, WARE, SETTLEMENTS & GSH databases).
The Electricity Market Management System (EMMS) and Gas Supply Hub (GSH) Pre-Production environment will be unavailable during the outage window.

Upon completion of the outage users will be required to log in to the GSH Trayport application using their Production credentials.Trayport passwords in Pre-Production environment will be replaced with their Production passwords
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
114932NON-CONFORMANCE22/02/2024 05:55:17 AM

NON-CONFORMANCE Region VIC1 Thursday, 22 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 22 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MERCER01
Duration: 22/02/2024 05:40 to 22/02/2024 05:55
Amount: 127 MW
Constraint: NC-V_MERCER01

Auto-generated on behalf of Manager NEM Real Time Operations
114931NON-CONFORMANCE22/02/2024 04:30:13 AM

NON-CONFORMANCE Region NSW1 Thursday, 22 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 22 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 22/02/2024 04:20 to 22/02/2024 04:30
Amount: -29 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
114912NON-CONFORMANCE21/02/2024 05:16:04 AM

NON-CONFORMANCE Region QLD1 Wednesday, 21 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 21 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YABULU2
Duration: 21/02/2024 04:30 to 21/02/2024 05:15
Amount: 41 MW
Constraint: NC-Q_YABULU2

Auto-generated on behalf of Manager NEM Real Time Operations
114911NON-CONFORMANCE21/02/2024 05:15:13 AM

NON-CONFORMANCE Region QLD1 Wednesday, 21 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 21 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YABULU
Duration: 21/02/2024 04:30 to 21/02/2024 05:15
Amount: 75 MW
Constraint: NC-Q_YABULU

Auto-generated on behalf of Manager NEM Real Time Operations
114894NON-CONFORMANCE20/02/2024 05:15:16 PM

NON-CONFORMANCE Region NSW1 Tuesday, 20 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 20 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP2
Duration: 20/02/2024 17:10 to 20/02/2024 17:15
Amount: 27 MW
Constraint: NC-N_MP2

Auto-generated on behalf of Manager NEM Real Time Operations
114889CONSTRAINTS20/02/2024 07:23:40 AM

Update to system strength constraints in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 110677

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of new feeder 8905 (H13 Ross - H39 Woree) 275kV line in Far North Queensland, the system normal system strength equations for low North Queensland demands and all Karreya stations out of service conditions have been revised.

A revision to the constraint equations will be implemented at 1400 hrs on Tuesday 20th February 2024.

The new system strength combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases.

Below constraint equations in the Q-NIL set will be modified:

- Q_NIL_STRGTH_KBWF
- Q_NIL_STRGTH_KBWF_I
- Q_NIL_STRGTH_HAUSF
- Q_NIL_STRGTH_HAUSF_I
- Q_NIL_STRGTH_MEWF
- Q_NIL_STRGTH_MEWF_I

AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm