Filter by category
Filter by Date
Update: Forecast Lack Of Reserve Level 2 (LOR2) in the South Australia region - STPASA - 04/07/2016
RE: AEMO Electricity Market Notice No. 54157.
NOTICE OF UPDATE
AEMO declares forecast LOR2 conditions for the South Australia region for the following periods:
From 04/07/2016 1800 hrs to 2000 hrs
The contingency capacity reserve required is 200 MW
The minimum reserve available is 110 MW
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Harmohan Singh
Operations Planning
Forecast Lack Of Reserve Level 2 (LOR2) in the South Australia region - STPASA - 04/07/2016
AEMO declares a Forecast LOR2 condition for the South Australia region for the following period:
From 04/07/2016 1800 hrs to 1900 hrs
The contingency capacity reserve required is 200 MW
The minimum reserve available is 165 MW
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Operations Planning
Update - Raise Regulation FCAS Increased - 27/06/16
Update - Variation to FCAS regulation requirements: NEM Global - 27/06/16.
Refer to MN 54151
FCAS Raise regulation requirements were increased to manage time error to within standards.
The following constraints were invoked to manage raise regulation requirements.
F-MAIN_RREG_0350 invoked from 1650 hrs to 1735 hrs
Manager NEM Real Time Operations
Raise Regulation FCAS Increased - 27/06/16
Variation to FCAS regulation requirements: NEM Global - 27/06/16.
FCAS Raise regulation requirements have been increased to manage time error to within standards.
The following constraints have been invoked to manage raise regulation requirements.
F-MAIN_RREG_0350 invoked from 1650 hrs until further notice.
Manager NEM Real Time Operations
Update - Raise Regulation FCAS Increased - 24/06/16
Update to MArket Notice 53974
Variation to FCAS regulation requirements: NEM Global - 24/06/16.
Constraint Set F-MAIN_RREG_0350 was revoked at 1700 hrs..
Manager NEM Real Time Operations
Raise Regulation FCAS Increased - 24/06/16
Variation to FCAS regulation requirements: NEM Global - 24/06/16.
FCAS Raise regulation requirements have been increased to manage time error to within standards.
The following constraints have been invoked to manage raise regulation requirements.
F-MAIN_RREG_0350 invoked from 1555 hrs until further notice.
Manager NEM Real Time Operations
Network Augmentation Commissioned - South Australia Region - 15 June 2016
Network Augmentation Commissioned - South Australia Region - 15 June 2016
A network augmentation has been commissioned in the South Australia Region
The Mt Lock 275 kV Sub Station was commissioned at 1630 hrs 15 June 2016. Mt Lock substation has been cut into the former Canowie - Davenport 275 kV Line to form two new transmission lines, Canowie - Mt Lock 275 kV Line and Davenport - Mt Lock 275 kV Line.
Manager NEM Real Time Operations
Basslink Availability
Basslink Availability
Basslink restored to full operation at 1151 hrs Monday, 13 June 2016
Manager NEM Real Time Operations
Changes to raise FCAS requirements in Tasmania
Changes to raise FCAS requirements in Tasmania
Refer to AEMO Electricity market notice 51618
The adaptive under-frequency load shedding scheme (AUFLS) was implemented in January 2016 to reduce the contingency raise FCAS requirements in Tasmania. TasNetworks has advised AEMO this scheme was disabled at 1000 hrs 8 June 2016. Tasmanian contingency FCAS requirements now do not use the reduction provided by this scheme.
Ben Blake
AEMO Operations