Market Notices

115157RESERVE NOTICE26/02/2024 05:34:52 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115135 has been updated at 1740 hrs 26/02/2024 to the following:

[1.] From 1430 hrs 29/02/2024 to 1930 hrs 29/02/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 243 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
115153RESERVE NOTICE26/02/2024 04:45:58 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1730 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 729 MW.
The minimum capacity reserve available is 355 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
115135RESERVE NOTICE26/02/2024 02:14:06 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115132 has been updated at 1300 hrs 26/02/2024 to the following:

From 1630 hrs to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 324 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115132RESERVE NOTICE26/02/2024 11:41:30 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115130 has been updated at 1100 hrs 26/02/2024 to the following:

From 1630 hrs to 1830 hrs 29/02/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 230 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115130RESERVE NOTICE26/02/2024 10:04:05 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1800 hrs 29/02/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 678 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115068RESERVE NOTICE24/02/2024 02:33:26 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115063 is cancelled at 0230 hrs 24/02/2024

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM RTO
115063RESERVE NOTICE23/02/2024 11:47:47 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1630 hrs 29/02/2024 to 1800 hrs 29/02/2024.
The forecast capacity reserve requirement is 750 MW.
The minimum capacity reserve available is 650 MW.

[2.] From 1830 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 1050 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
114889CONSTRAINTS20/02/2024 07:23:40 AM

Update to system strength constraints in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 110677

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of new feeder 8905 (H13 Ross - H39 Woree) 275kV line in Far North Queensland, the system normal system strength equations for low North Queensland demands and all Karreya stations out of service conditions have been revised.

A revision to the constraint equations will be implemented at 1400 hrs on Tuesday 20th February 2024.

The new system strength combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases.

Below constraint equations in the Q-NIL set will be modified:

- Q_NIL_STRGTH_KBWF
- Q_NIL_STRGTH_KBWF_I
- Q_NIL_STRGTH_HAUSF
- Q_NIL_STRGTH_HAUSF_I
- Q_NIL_STRGTH_MEWF
- Q_NIL_STRGTH_MEWF_I

AEMO Operations
114589RESERVE NOTICE13/02/2024 01:52:07 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:

[1.] From 1430 hrs 13/02/2024 to 1600 hrs 13/02/2024.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 384 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations