Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 06/03/2023
Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 06/03/2023
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR2 condition is forecast to exist until 1730 hrs.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 611 MW.
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement a AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the QLD region - 31/01/2023
The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.105421 is cancelled at 1940 hrs 31/01/2023.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 31/01/2023
Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 31/01/2023
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1900 hrs.
The Actual LOR2 condition is forecast to exist until 1930 hrs.
The forecast capacity reserve requirement is 500 MW.
The minimum capacity reserve available is 440 MW.
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the QLD region - 13/08/2022
Cancellation of Actual (LOR2) condition in the QLD region - 13/08/2022
The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.100929 is cancelled at 0845 hrs 13/08/2022.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the Qld region - 05/07/2022
The Actual LOR2 Condition in the Qld Region advised in AEMO Electricity Market Notice No.99972 is cancelled at 0920 hrs 05/07/2022
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 05/07/2022
Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 05/07/2022
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 0830 hrs.
The Actual LOR2 condition is forecast to exist until 0900 hrs.
The forecast capacity reserve requirement is 509 MW.
The minimum capacity reserve available is 401 MW.
AEMO is seeking an immediate market response.
Manager NEM Real Time Operations
Final - Market suspension - FCAS prices
In accordance with Market notices 99065 and 99070, the zero ancillary services prices to TIs 0805 - 0900 on 23 June 2022 for all services in all regions have been replaced with the corresponding ROP values for each TI, service, and region.
Manager NEM Real Time Operations
Declaration of electricity market resumption
Declaration of electricity market resumption
Refer initial AEMO Electricity Market Notice 97704
AEMO declares that the suspension of the spot market in New South Wales, Queensland, South Australia, Tasmania and Victoria will end at 1400 hrs on 24 June 2022.
Relevant Market Notices issued under this suspension:
97704 and 98805
Manager NEM Real Time Operations
Update - Market suspension - FCAS prices
Update - Market suspension - FCAS prices
Refer to Market Notice 99070
AEMO has determined that there is no basis on which the published ancillary service prices for TI 0405 to TI 0800 on 23 June 2022 can be substituted, and accordingly the published ancillary service prices for those TIs in all regions will stand.
Manager NEM Real Time Operations