Market Notices

116739NON-CONFORMANCE21/05/2024 05:01:14 PM

NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 21/05/2024 16:30 to 21/05/2024 16:35
Amount: -19 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
     
116738NON-CONFORMANCE21/05/2024 05:00:17 PM

NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 21/05/2024 10:45 to 21/05/2024 10:50
Amount: -22 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
     
116735INTER-REGIONAL TRANSFER21/05/2024 08:20:42 AM

Update Inter-Regional Transfer limit variation - Basslink 21/05/2024

AEMO ELECTRICITY MARKET NOTICE

Update Inter-Regional Transfer limit variation - Basslink

Refer AEMO Electricity Market Notice 116734

There was an unplanned outage of the Basslink interconnector at 0235 hrs. The Basslink interconnector has been returned to service.

The following constraint set was revoked at 0810 hrs 21/05/2024

I-BL_ZERO

The constraint set contains the following interconnector on the left hand side.

T-V-MNSP1

Manager NEM Real Time Operations
     
116734INTER-REGIONAL TRANSFER21/05/2024 02:51:33 AM

Inter-Regional Transfer limit variation - Basslink 21/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Basslink

There has been an unplanned outage of the Basslink interconnector at 0235 hrs

The following constraint set was invoked at 0240 hrs 21/05/2024

I-BL_ZERO

The constraint set contains the following interconnector on the left hand side.

T-V-MNSP1

Manager NEM Real Time Operations
     
116733RESERVE NOTICE20/05/2024 07:13:45 PM

Cancellation of Actual (LOR1) condition in the NSW region - 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 20/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116730 is cancelled at 1910 hrs 20/05/2024.

Manager NEM Real Time Operations
     
116730RESERVE NOTICE20/05/2024 05:17:20 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1630 MW
The minimum capacity reserve available is 1028 MW

Manager NEM Real Time Operations
     
116696NON-CONFORMANCE19/05/2024 07:40:16 AM

NON-CONFORMANCE Region QLD1 Sunday, 19 May 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 19 May 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: PUMP2
Duration: 19/05/2024 07:35 to 19/05/2024 07:40
Amount: 240 MW
Constraint: NC-Q_PUMP2

Auto-generated on behalf of Manager NEM Real Time Operations
     
116689RESERVE NOTICE18/05/2024 06:42:10 PM

Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116688 is cancelled at 1840 hrs 18/05/2024.

Manager NEM Real Time Operations
     
116688RESERVE NOTICE18/05/2024 05:58:11 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1314 MW

Manager NEM Real Time Operations
     