Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region.
An Actual LOR1 condition has been declared for the NSW Region.
From 1330 hrs to 1700 hrs Monday, 6 February 2017
The contingency capacity reserve required is 1330 MW
The minimum reserve available is 1010 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the South Australia region - 6/1/17
Correction to Market notice 56660 - should be type Market notice type Reserve Notice.
Cancellation of Actual (LOR1) condition in the South Australia region - 6/1/17
The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice No.56660 is cancelled at 1745 hrs 6/1/17.
Manager NEM Real Time Operations
Cancellation - Forecast Lack Of Reserve Level 2 (LOR2) in the SA region - STPASA - 06/01/2017
Cancellation - Forecast Lack Of Reserve Level 2 (LOR2) in the SA region - STPASA - 06/01/2017
Refer to MN 56554
AEMO cancels the Forecast LOR2 condition for the SA region.
From 1630 hrs to 1700 hrs 06/01/2017
Manager NEM Real Time Operations
Forecast Lack Of Reserve Level 2 (LOR2) in the SA region - STPASA - 06/01/2017
Forecast Lack Of Reserve Level 2 (LOR2) in the SA region - STPASA - 06/01/2017
AEMO declares a Forecast LOR2 condition for the SA region.
From 1630 hrs to 1700 hrs 06/01/2017
The contingency capacity reserve required is 200 MW
The minimum reserve available is 195 MW
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through a AEMO intervention event.
Manager NEM Real Time Operations
Forecast Lack Of Reserve Level 2 (LOR2) in South Australia region - 23/12/16
Refer to AEMO Electricity Market Notice 56397
Forecast Lack Of Reserve Level 2 (LOR2) in South Australia Region - from 0700 hrs to 1330 hrs on 23/12/2016.
AEMO declares a Forecast LOR2 condition for the South Australia region during the short notice outage of the Moorabool - Mortlake PS 500 kV Line in Victoria region, from 0700 hrs to 1330 hrs 23/12/16.
On the occurrence of a credible contingency during this planned outage, South Australia region could separate from the rest of the NEM and is likely to result in interruptions to power supplies in South Australia.
There are sufficient capacity reserves in the South Australia region to meet electricity demand but following the next credible contingency it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing interruptions to power supplies in South Australia.
Manager NEM Real Time Operations
Forecast Lack Of Reserve Level 2 (LOR2) in South Australia region - 22/12/16
AEMO ELECTRICITY MARKET NOTICE
Refer to AEMO Electricity Market Notice 56379
Forecast Lack Of Reserve Level 2 (LOR2) in South Australia Region - from 0600 hrs to 1530 hrs on 22/12/2016.
AEMO declares a Forecast LOR2 condition for the South Australia region during the planned outage of Heywood - Tarrone PS 500k V line in Victoria region, from 0600 hrs to 1530 hrs 22/12/2016.
On the occurrence of a credible contingency during this planned outage, South Australia region could separate from the rest of the NEM and is likely to result in interruptions to power supplies in South Australia.
There are sufficient capacity reserves in the South Australia region to meet electricity demand but following the next credible contingency it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing interruptions to power supplies in South Australia.
Manager NEM Real Time Operations
Forecast Lack Of Reserve Level 2 (LOR2) in South Australia region - 14 to 15 Dec 2016
Refer to AEMO Market Notice 55727
Forecast Lack Of Reserve Level 2 (LOR2) in South Australia Region - from 0600 hrs on 14/12/2016 to 1600 hrs on 15/12/2016.
AEMO declares Forecast LOR2 conditions for the South Australia region during the planned outage of Heywood No.1 500 kV busbar in Victoria region, from 0600 hrs on 14/12/2016 to 1600 hrs on 15/12/2016.
On the occurrence of a credible contingency during this planned outage, South Australia region could separate from the rest of the NEM and is likely to result in interruptions to power supplies in South Australia.
There are sufficient capacity reserves in the South Australia region to meet electricity demand but following the next credible contingency it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing interruptions to power supplies in South Australia.
Harmohan Singh
Operations Planning
Forecast Lack Of Reserve Level 2 (LOR2) in South Australia Region - 30 Nov to 01 Dec 2016
Refer to AEMO Market Notice 55515
Forecast Lack Of Reserve Level 2 (LOR2) in South Australia Region - from 0600 hrs on 30/11/2016 to 1600 hrs on 01/12/2016.
AEMO declares Forecast LOR2 conditions for the South Australia region during the planned outage of Heywood No.2 500 kV busbar from 0600 hrs on 30/11/2016 to 1600 hrs on 01/12/2016.
On the occurrence of a credible contingency during these planned outage, South Australia region could separate from the rest of the NEM and is likely to result in interruptions to power supplies in South Australia.
There are sufficient capacity reserves in the South Australia region to meet electricity demand but following the next credible contingency it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing interruptions to power supplies in South Australia.
Operations Planning
Bhishma Chhetri
Forecast Lack of Reserve Level 2 (LOR2) in South Australia from 22 Nov 2016 to 26 Nov 2016
Refer to AEMO Market Notices: 55466.
Forecast Lack Of Reserve Level 2 (LOR2) in South Australia Region starting from 0700hrs 22/11/2016 to 1700hrs 26/11/2016.
AEMO declares Forecast LOR2 conditions in the South Australia region for the above period. During this period, an outage is scheduled for Heywood to South East No.1 275 kV transmission line between Victoria and South Australia.
On the occurrence of a credible contingency during this outage, South Australia region could separate from the rest of the NEM and is likely to result in interruptions to power supply in South Australia.
There are sufficient capacity reserves in the South Australia region to meet electricity demand but following the next credible contingency it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing interruptions to power supplies in South Australia.
Catherine Wu
AEMO Operations