Market Notices

54151GENERAL NOTICE27/06/2016 04:55:35 PM

Raise Regulation FCAS Increased - 27/06/16

AEMO ELECTRICITY MARKET NOTICE

Variation to FCAS regulation requirements: NEM Global - 27/06/16.

FCAS Raise regulation requirements have been increased to manage time error to within standards.

The following constraints have been invoked to manage raise regulation requirements.

F-MAIN_RREG_0350 invoked from 1650 hrs until further notice.

Manager NEM Real Time Operations
54129GENERAL NOTICE24/06/2016 05:02:29 PM

Update - Raise Regulation FCAS Increased - 24/06/16

AEMO ELECTRICITY MARKET NOTICE

Update to MArket Notice 53974

Variation to FCAS regulation requirements: NEM Global - 24/06/16.

Constraint Set F-MAIN_RREG_0350 was revoked at 1700 hrs..

Manager NEM Real Time Operations
54128GENERAL NOTICE24/06/2016 03:53:42 PM

Raise Regulation FCAS Increased - 24/06/16

AEMO ELECTRICITY MARKET NOTICE

Variation to FCAS regulation requirements: NEM Global - 24/06/16.

FCAS Raise regulation requirements have been increased to manage time error to within standards.

The following constraints have been invoked to manage raise regulation requirements.

F-MAIN_RREG_0350 invoked from 1555 hrs until further notice.

Manager NEM Real Time Operations
53974GENERAL NOTICE15/06/2016 05:38:09 PM

Network Augmentation Commissioned - South Australia Region - 15 June 2016

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - South Australia Region - 15 June 2016

A network augmentation has been commissioned in the South Australia Region

The Mt Lock 275 kV Sub Station was commissioned at 1630 hrs 15 June 2016. Mt Lock substation has been cut into the former Canowie - Davenport 275 kV Line to form two new transmission lines, Canowie - Mt Lock 275 kV Line and Davenport - Mt Lock 275 kV Line.


Manager NEM Real Time Operations
53959GENERAL NOTICE13/06/2016 12:10:02 PM

Basslink Availability

AEMO ELECTRICITY MARKET NOTICE

Basslink Availability

Basslink restored to full operation at 1151 hrs Monday, 13 June 2016


Manager NEM Real Time Operations
53746GENERAL NOTICE08/06/2016 03:30:57 PM

Changes to raise FCAS requirements in Tasmania

AEMO ELECTRICITY MARKET NOTICE

Changes to raise FCAS requirements in Tasmania

Refer to AEMO Electricity market notice 51618

The adaptive under-frequency load shedding scheme (AUFLS) was implemented in January 2016 to reduce the contingency raise FCAS requirements in Tasmania. TasNetworks has advised AEMO this scheme was disabled at 1000 hrs 8 June 2016. Tasmanian contingency FCAS requirements now do not use the reduction provided by this scheme.

Ben Blake
AEMO Operations
53660GENERAL NOTICE06/06/2016 08:19:53 PM

Constraint Automation to Manage Power Security in Vic Region.

AEMO ELECTRICITY MARKET NOTICE

Constraint Automation to Manage Power Security in Vic Region, Monday, 06 June 2016.

AEMO network analysis indicated that the trip of the Hazelwood Power station to Hazelwood Terminal station No.2 220 kV line would result in an overload of the Hazelwood Power station to Hazelwood Terminal station A1 500 / 220 kV transformer.

AEMO invoked automated constraint set CA_SPS_4667C455 from 1850 to 1905 hrs to manage power system security.


Manager NEM Real Time Operations
53547GENERAL NOTICE27/05/2016 02:26:09 PM

Planned outage of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line - Victoria Region on 29 May 2016

AEMO ELECTRICITY MARKET NOTICE.

This market notice is FOR INFORMATION ONLY.

There is short notice planned outage of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line between 0630-1600hrs on 29 May 2016 in Victoria region.

During this outage, following the next contingency (trip of the Moorabool-Sydenham No.2 500 kV line) South Australia region still remains connected to the NEM. However if this contingency occurs, AEMO will invoke the following FCAS regulation constraint sets to secure the power system in South Australia region:

F-S_LREG_0035
F-S_RREG_0035

Please also refer to market notice 52838.

Refer to AEMO Network Outage Schedule (NOS) for further details

Operations Planning
53538GENERAL NOTICE27/05/2016 12:43:22 AM

Cancellation - Brisbane Communication Issues - 27th May 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Brisbane Communication Issues - 27th May 2016

Refer to MN 53535

This is to advise that the problems on the AEMO Brisbane Control Centre Phone system have been resolved.

Participants may noiw use normal Brisbane Control Centre and Sydney Control Centre contact numbers.