116299POWER SYSTEM EVENTS24/04/2024 10:54:59 AM

Non-credible contingency event - QLD region - 24/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 24/04/2024

At 0855 hrs the Ross - Guybal Munjan 8916 275 kV line tripped at the Guybal Munjan end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.


Manager NEM Real Time Operations
     
116292PRICES UNCHANGED23/04/2024 03:04:29 PM

[EventId:202404231435_confirmed] Prices for interval 23-Apr-2024 14:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 23 April 2024

PRICES ARE NOW CONFIRMED for trading interval 23-Apr-2024 14:35.

In accordance with Market Notice 116281 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116291PRICES UNCHANGED23/04/2024 03:03:36 PM

[EventId:202404231500_confirmed] Prices for interval 23-Apr-2024 15:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 23 April 2024

PRICES ARE NOW CONFIRMED for trading interval 23-Apr-2024 15:00.

In accordance with Market Notice 116286 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116290PRICES UNCHANGED23/04/2024 03:02:14 PM

[EventId:202404231455_confirmed] Prices for interval 23-Apr-2024 14:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 23 April 2024

PRICES ARE NOW CONFIRMED for trading interval 23-Apr-2024 14:55.

In accordance with Market Notice 116285 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116289PRICES UNCHANGED23/04/2024 03:05:29 PM

[EventId:202404231450_confirmed] Prices for interval 23-Apr-2024 14:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 23 April 2024

PRICES ARE NOW CONFIRMED for trading interval 23-Apr-2024 14:50.

In accordance with Market Notice 116284 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116288PRICES UNCHANGED23/04/2024 03:01:19 PM

[EventId:202404231445_confirmed] Prices for interval 23-Apr-2024 14:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 23 April 2024

PRICES ARE NOW CONFIRMED for trading interval 23-Apr-2024 14:45.

In accordance with Market Notice 116283 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116287PRICES UNCHANGED23/04/2024 03:00:15 PM

[EventId:202404231440_confirmed] Prices for interval 23-Apr-2024 14:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 23 April 2024

PRICES ARE NOW CONFIRMED for trading interval 23-Apr-2024 14:40.

In accordance with Market Notice 116282 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116276POWER SYSTEM EVENTS23/04/2024 12:09:41 PM

Non-credible contingency event - VIC region - 23/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 23/04/2024

At 1056 hrs the MOPS 11 Gen TX 2 Bus 500kV CB and the Dundonnell WF tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.


Manager NEM Real Time Operations
     
116257PRICES UNCHANGED22/04/2024 09:04:12 AM

[EventId:202404220835_confirmed] Prices for interval 22-Apr-2024 08:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 22 April 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Apr-2024 08:35.

In accordance with Market Notice 116241 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     