Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 116631
The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 17/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 16/05/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 17/05/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
[EventId:202405150700_review] Prices for interval 15-May-2024 07:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0655 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 07:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150655_review] Prices for interval 15-May-2024 06:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0650 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150650_review] Prices for interval 15-May-2024 06:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0645 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150645_review] Prices for interval 15-May-2024 06:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0640 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150640_review] Prices for interval 15-May-2024 06:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0635 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150635_review] Prices for interval 15-May-2024 06:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0630 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
CHG0089066 | Production | Dispatch Applications Upgrade
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: Dispatch Applications Upgrade
Change Start Date & Time: 22/05/2024 08:00:00 AEST
Change End Date & Time: 24/05/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements:
Under this change , AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch ,5-Minute Predispatch ,Predispatch, PD7 and PASA as part of the Integrating Energy Storage Systems project (IESS). This change will become effective upon rule commencement on 3 June, 2024.
No outage required.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.