116639SETTLEMENTS RESIDUE16/05/2024 05:45:28 PM

[EventId:202405161745_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 16 May 2024 17:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 May 2024.

Refer to market notice: 116637

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1745 hrs on 16 May 2024.

This is an AEMO autogenerated Market Notice.
     
116637SETTLEMENTS RESIDUE16/05/2024 05:30:33 PM

[EventId:202405161730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 May 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 May 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 May 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 16 May 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
116623PRICES SUBJECT TO REVIEW15/05/2024 06:55:24 AM

[EventId:202405150700_review] Prices for interval 15-May-2024 07:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0655 hrs on 15 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 07:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116622PRICES SUBJECT TO REVIEW15/05/2024 06:50:19 AM

[EventId:202405150655_review] Prices for interval 15-May-2024 06:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0650 hrs on 15 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116621PRICES SUBJECT TO REVIEW15/05/2024 06:45:18 AM

[EventId:202405150650_review] Prices for interval 15-May-2024 06:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0645 hrs on 15 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116620PRICES SUBJECT TO REVIEW15/05/2024 06:40:23 AM

[EventId:202405150645_review] Prices for interval 15-May-2024 06:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0640 hrs on 15 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116619PRICES SUBJECT TO REVIEW15/05/2024 06:35:21 AM

[EventId:202405150640_review] Prices for interval 15-May-2024 06:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0635 hrs on 15 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116618PRICES SUBJECT TO REVIEW15/05/2024 06:30:15 AM

[EventId:202405150635_review] Prices for interval 15-May-2024 06:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0630 hrs on 15 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116614MARKET SYSTEMS14/05/2024 02:41:56 PM

CHG0089066 | Production | Dispatch Applications Upgrade

Change Number: CHG0089066
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: Dispatch Applications Upgrade
Change Start Date & Time: 22/05/2024 08:00:00 AEST
Change End Date & Time: 24/05/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements:
Under this change , AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch ,5-Minute Predispatch ,Predispatch, PD7 and PASA as part of the Integrating Energy Storage Systems project (IESS). This change will become effective upon rule commencement on 3 June, 2024.

No outage required.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm