Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Duration: 27/04/2024 22:28 until further notice
Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 26/04/2024
Update - Non-credible contingency event - NSW region - 26/04/2024
Refer AEMO Electricity Market Notice 116339.
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: NSW
Elements: Griffith to Darlington Point 132kV line (99K) and the Darlington Point BESS
Duration: 1215 hrs 26/04/2024 until further notice
Constraint set(s) invoked: NIL
Manager NEM Real Time Operations
[EventId:202404241735_review] Prices for interval 24-Apr-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241730_review] Prices for interval 24-Apr-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241725_review] Prices for interval 24-Apr-2024 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241720_review] Prices for interval 24-Apr-2024 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241715_review] Prices for interval 24-Apr-2024 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241710_review] Prices for interval 24-Apr-2024 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404241405_review] Prices for interval 24-Apr-2024 14:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 24 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Apr-2024 14:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.