Market Notices

106716RESERVE NOTICE16/03/2023 05:54:35 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 16/03/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 16/03/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1750 hrs.
The Actual LOR2 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 372 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement a AEMO intervention event.

Manager NEM Real Time Operations
106658PRICE ADJUSTMENT15/03/2023 03:07:21 PM

[EventId:202303141455_confirmed] Prices for interval 14-Mar-2023 14:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1507 hrs on 15 March 2023

PRICES ARE NOW CONFIRMED for trading interval 14-Mar-2023 14:55.

In accordance with Market Notice 106608 AEMO has reviewed this trading interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
RAISEREG
TAS1 $5.68 $42.74


This is an AEMO autogenerated Market Notice.
106503RECALL GEN CAPACITY13/03/2023 10:42:16 AM

Request for Generator Recall Information for 16/03/2023 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 106497.

Please provide Generator Recall Information for 16/03/2023 by 1100 hrs AEST on 14/03/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
106502RECALL GEN CAPACITY13/03/2023 10:41:14 AM

Request for Generator Recall Information for 16/03/2023 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 106498.

Please provide Generator Recall Information for 16/03/2023 by 1100 hrs AEST on 14/03/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
106312RESERVE NOTICE06/03/2023 06:50:22 PM

Cancellation of Actual (LOR2) condition in the NSW region - 06/03/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 06/03/2023

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 106310 is cancelled at 1850 hrs 06/03/2023.

Manager NEM Real Time Operations
106310RESERVE NOTICE06/03/2023 05:31:44 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 06/03/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 06/03/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR2 condition is forecast to exist until 1730 hrs.

The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 611 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement a AEMO intervention event.

Manager NEM Real Time Operations

105435RECALL GEN CAPACITY01/02/2023 09:50:53 AM

Request for Generator Recall Information for 03/02/2023 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice 105433.

Please provide Generator Recall Information for 03/02/2023 by 1700 hrs AEST on 01/02/2023 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://www.aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
105423RESERVE NOTICE31/01/2023 07:44:10 PM

Cancellation of Actual (LOR2) condition in the QLD region - 31/01/2023

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.105421 is cancelled at 1940 hrs 31/01/2023.

Manager NEM Real Time Operations
105421RESERVE NOTICE31/01/2023 07:16:51 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 31/01/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 31/01/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1900 hrs.

The Actual LOR2 condition is forecast to exist until 1930 hrs.

The forecast capacity reserve requirement is 500 MW.
The minimum capacity reserve available is 440 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations