109581RESERVE NOTICE04/09/2023 05:47:18 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/09/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/09/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.


The capacity reserve requirement is 1492 MW
The minimum capacity reserve available is 1239 MW

Manager NEM Real Time Operations
109190RESERVE NOTICE02/08/2023 08:16:45 PM

Cancellation of Actual (LOR1) condition in the NSW region - 02/08/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 02/08/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.109186 is cancelled at 2000 hrs 02/08/2023.

Manager NEM Real Time Operations
109186RESERVE NOTICE02/08/2023 05:20:52 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/08/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/08/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 826 MW.


Manager NEM Real Time Operations
109155RESERVE NOTICE01/08/2023 08:10:44 AM

Cancellation of Actual (LOR1) condition in the NSW region - 01/08/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 01/08/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.109154 is cancelled at 0810 hrs 01/08/2023.

Manager NEM Real Time Operations
109154RESERVE NOTICE01/08/2023 07:40:55 AM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 01/08/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/08/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 0730 hrs.

The Actual LOR1 condition is forecast to exist until 0800 hrs.

The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1204 MW.


Manager NEM Real Time Operations
109011RESERVE NOTICE20/07/2023 08:21:58 PM

Cancellation of Actual (LOR1) condition in the NSW region - 20/07/2023

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.109008 is cancelled at 2020 hrs 20/07/2023

Manager NEM Real Time Operations
109008RESERVE NOTICE20/07/2023 05:50:38 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/07/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/07/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.

The Actual LOR1 condition is forecast to exist until 2030 hrs.

The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1046 MW.


Manager NEM Real Time Operations
108986RESERVE NOTICE19/07/2023 08:58:27 PM

Cancellation of Actual (LOR1) condition in the NSW region - 19/07/2023

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.108984 is cancelled at 2050 hrs 19/07/2023

Manager NEM Real Time Operations
108984RESERVE NOTICE19/07/2023 06:36:22 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/07/2023

AEMO ELECTRICITY MARKET NOTICE

The actual LOR1 condition in the NSW region advised in AEMO Electricity Market
Notice No. 108983 has been updated at 1830 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2100 hrs.

The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 964 MW.

Manager NEM Real Time Operations