Update - Non-credible contingency event - Torrens Island 66 kV East Bus - SA region - 22/09/2021
Update - Non-credible contingency event - Torrens Island 66 kV East Bus - SA region - 22/09/2021
At 1740 hrs the Torrens Island 66 kV East bus tripped. The bus was returned to service at 1846 hrs.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Refer AEMO Electricity Market Notice 90963
Manager NEM Real Time Operations
Non-credible contingency event - SA region - 22/09/2021
Non-credible contingency event - SA region - 22/09/2021
At 1740 hrs the Torrens Island 66 kV East busbar tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - VIC region - 22/09/2021
Update - Non-credible contingency event - VIC region - 22/09/2021
At 0916 hrs the Springvale No. 1 220 kV busbar tripped.
Refer AEMO ELECTRICITY MARKET NOTICE MN90937 and MN90939
At 0925 hrs the Springvale No. 1 220 kV busbar was returned to service.
Further investigation has identified that this was a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - 22/09/2021
Non-credible contingency event - SA region - 22/09/2021
At 1134 hrs the No. 1 and No. 2 275 kV Static Var Compensator (SVC) at South East Substation tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
The following constraint set was invoked at 1145 hrs
S-X_SEVC2+PAVC
The constraint sets contain equations with the following interconnector on the LHS:
V-S-MNSP1
V-SA
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Update - Non-credible contingency event - VIC region - 22/09/2021
Update - Non-credible contingency event - VIC region - 22/09/2021
At 0916 hrs the Springvale No. 1 220 kV busbar tripped.
Refer AEMO ELECTRICITY MARKET NOTICE MN90937
At 0925 hrs the Springvale No. 1 220 kV busbar was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 22/09/2021
Non-credible contingency event - VIC region - 22/09/2021
At 0916 hrs the Springvale No. 1 220 kV busbar tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - Qld region - 12/09/2021
Update - Non-credible contingency event - Qld region - 12/09/2021
Refer AEMO Electricity Market Notice 90396
At 2215 hrs the Ross - Townsville South 7249 132 kV line tripped and auto-reclosed and the Kennedy Energy Park Wind Farm tripped.
The cause of this non credible contingency has been identified. AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - Qld region - 12/09/2021
Non-credible contingency event - Qld region - 12/09/2021
At 2215 hrs the Ross - Townsville South 7249 132 kV line tripped and auto-reclosed and the Kennedy Energy Park Wind Farm tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - 12/09/2021
At 1822 hrs at Canowie substation circuit breakers CB 6501 and CB 6502 tripped which resulted in the following:
Opening of the Canowie - Robertstown 275 kV Line at the Canowie end only
Opening of the Canowie - Mt Lock 275 kV Line at the Canowie end only
Disconnection of Hallett substation and Hallet WF
At 1826 hrs CB 6501 at Canowie was manually closed which returned the Canowie - Robertstown 275 kV Line and the Canowie - Mt Lock 275 kV Line into service.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations