107305POWER SYSTEM EVENTS06/04/2023 07:11:14 PM

Non-credible contingency event - SA region - 06/04/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 06/04/2023

At 1814 hrs the Robertstown - North West Bend No 1 Line and the North West Bend - Monash - Berri No 1 Line tripped and auto reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
107205CONSTRAINTS03/04/2023 01:42:00 PM

Tasmanian Regulation FCAS changes - Wednesday 5th April 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO are changing the procurement of Regulation FCAS for the TAS region.

This change is based on advice received from TasNetworks, following a review of operation of the TAS region with the end of the reclassification of Basslink.

Refer to AEMO Electricity market notice 105443.

Following this change Regulation FCAS requirements for the TAS region will only be procured from within TAS.

This change will be implemented from 1000 on Wed 5th April.

Ben Blake
Manager Congestion & Grid Modelling
107160POWER SYSTEM EVENTS02/04/2023 09:46:00 AM

Non-credible contingency event - Qld region - 01/04/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - Qld region - 01/04/2023

At 1950 hrs 01/04/2023 there was an unplanned outage of Unit 5 and Unit 7 at H48 Braemar 2 Power Station.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
107152POWER SYSTEM EVENTS01/04/2023 09:52:09 PM

Non-credible contingency event - Qld region - 01/04/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - Qld region - 01/04/2023

At 2109 hrs ,
- Feeder 877 Woree -Tumoulin 275 kV - tripped and auto reclosed
- Feeder 7166 Chalumbin - Turkinje 132 kV - Tripped and auto reclosed
- Feeder 7143 Kamerunga - Barron Gorge - Tripped

AEMO did not instruct load shedding.

AEMO was advised of disconnection of bulk electrical load of 30 MW.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
107032POWER SYSTEM EVENTS27/03/2023 04:23:28 PM

Update - Non-credible contingency event - TAS region - 27/03/2023

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 27/03/2023

Refer AEMO Electricity market notice 106999

At 1040 hrs the Sheffield - Palmerston 220kV line tripped at the Palmerston end only.

The cause of this non credible contingency event is not known at this stage.

AEMO is not satisfied that this non credible event is unlikely to re-occur.

AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: Tas

Duration: 1227/03/2023 16:20 until further notice

Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
106999POWER SYSTEM EVENTS27/03/2023 12:27:13 PM

Non-credible contingency event - TAS region - 27/03/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 27/03/2023

At 1040 hrs the Sheffield - Palmerston 220kV line tripped at the Palmerston end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
106896POWER SYSTEM EVENTS23/03/2023 11:32:12 AM

Non-credible contingency event - SA region - 23/03/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 23/03/2023

At 1113 hrs the South East SVC 1 and SVC 2 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
106855CONSTRAINTS21/03/2023 08:14:08 AM

Update to Victorian system normal constraint equations ID

AEMO ELECTRICITY MARKET NOTICE

AEMO has been conducting major review of thermal constraint equations for preparation of completion of VNI East project. As part of the review, AEMO is going to update the constraint equations IDs to use the new standard format of below (this is the same standard now used in NSW):

V>>[OUTAGE]_[MONITORING ELEMENT]_[CONTINGENCY ELEMENT]

This is to improve the simplicity and readability of a thermal constraint equation ID.

Constraint equations ID in sets V-NIL and V-NIL_BATS_BETS_15M will be updated to the new format on Thursday 23rd March 2023 at 1000 hrs. The previous used constraint equations ID will be included in the Modification field of the constraint equation for reference.

The changes have now been implemented into AEMO's pre-production system.

Terry Liu
AEMO Operations
106643CONSTRAINTS15/03/2023 12:39:32 PM

Updated NSW system normal voltage stability limit

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 105936?

The Murraylink Very Fast Runback (VFRB) scheme was modified to increase the capacity of the network due to the increase in generation in the area. The scheme was changed so Murraylink VFRB could be activated / de-activated depending on the time of day on the monitored 220kV lines in north-west Victoria.?

Transgrid has advised AEMO on a revision to the X5 voltage collapse limit with this change to VFRB. This will now be managed by two limits.?

The following constraint equation changes will be implemented at 0900 hrs on Thursday 16th March 2023:
N^^N_NIL_X5_BEKG (replaces N^^N_NIL_3)
N^^N_NIL_X5_BESH (new)?

For full details on the factors on constraint equations and all the constraint equation changes - these have now been loaded into AEMO's pre-production systems.?

Ben Blake
AEMO Operations

X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm