Direction ceased - Victoria Region region 1/12/16
Direction - Victoria Region region 1/12/16
In accordance with clause 4.8.9 of the National Electricity Rules AEMO has issued a direction to a participant in the Victoria region.
The direction was necessary to re-establish the power system to a secure operating state,
The direction was issued at 1030 hrs and ceased at 1545hrs /1/2/16
Manager NEM Real Time Operations
AEMO Intervention Event intervention price dispatch intervals - 1/12/16
AEMO Intervention Event intervention price dispatch intervals - 1/12/16
Refer AEMO Electricity Market Notice no. 56046
An AEMO Intervention Event has been implemented by issuing a direction to re-establish the power system to a secure operating state.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
The AEMO Intervention Event commenced in the 1035 hrs dispatch interval.
Intervention pricing will not be implemented during these intervention price dispatch intervals.
Manager NEM Real Time Operations
Direction - Victoria Region region 1/12/16
Direction - Victoria Region region 1/12/16
In accordance with clause 4.8.9 of the National Electricity Rules AEMO has issued a direction to a participant in the Victoria region.
The direction was necessary to re-establish the power system to a secure operating state,
The direction was issued at 1030 hrs and is expected to stay in place until further notice
Manager NEM Real Time Operations
AEMO Intervention Event intervention price dispatch intervals - 1/12/16
AEMO Intervention Event intervention price dispatch intervals - 1/12/16
Refer AEMO Electricity Market Notice no. 55973 and 56015
An AEMO Intervention Event has been implemented by issuing a direction to maintain the power system in a secure operating state.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
The AEMO Intervention Event commenced in the 0135 hrs dispatch interval.
Intervention pricing will be implemented during these intervention price dispatch intervals from the 0135 hrs dispatch interval until the end of the AEMO Intervention Event at 0500 hrs 1/12/16
Manager NEM Real Time Operations
Cancellation of Directions - South Australia region 01/12/2016
Cancellation of Directions - South Australia region 01/12/2016
In accordance with clause 4.8.9 of the National Electricity Rules AEMO had issued directions to participants in the South Australia region.
The directions were necessary to maintain the power system in a secure operating state.
The directions are no longer required and have been cancelled from 0500 hrs 01/12/2016
Manager NEM Real Time Operations
Direction - South Australia region 01/12/2016
Direction - South Australia region 01/12/2016
In accordance with clause 4.8.9 of the National Electricity Rules AEMO has issued directions to participants in the South Australia region.
The directions were necessary to maintain the power system in a secure operating state.
The directions was issued from 0130 hrs 01/12/2016 and will remain in place until further notice.
Manager NEM Real Time Operations
AEMO advises that South Australia has seperated from the NEM
POWER SYSTEM EVENT
At 0016 hrs 1st December 2016 the SA power system seperated from the NEM but remains operating as a separate entity. AEMO are investigating the cause and will develop and implement a reconnection plan as soon as practical.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 30 Nov 2016
Non-credible contingency event - NSW region - 30 Nov 2016
At 0039 hrs the Liddell-Tomago No. 82 line tripped at the Tomago end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Non-credible contingency event - Queensland region - 14 Nov 2016
Non-credible contingency event - Queensland region - 14 Nov 2016
At 2034 hrs the Innisfail No2 132 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations