Market Notices

114687INTER-REGIONAL TRANSFER14/02/2024 01:30:25 AM

Inter-regional transfer limit variation: South Morang - Sydenham No 1 and 2 500 kV lines (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

The South Morang - Sydenham No 1 and 2 500 kV lines have been de-energised to manage voltages in the Victoria region.

The following constraint set was invoked at 0105 hrs 14/02/2024

V-SMSY

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further details

Manager NEM Real Time Operations
114686INTER-REGIONAL TRANSFER14/02/2024 01:24:53 AM

Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - VIC region - 13/02/2024 -

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - 13/02/2024

At 1308 hrs 13/02/2024 the Moorabool - Sydenham No1 and No2 500 kV lines tripped.

Refer Market notices 114577 and 114625.

The following constraint set(s) are invoked :

V-X_MLSY
F-V-X_ML_BUSTIE_500
I-VS_050

These constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1

Refer to the Network outage scheduler (NOS) for more details:

Manager NEM Real Time Operations
114632RESERVE NOTICE13/02/2024 03:19:41 PM

Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024

The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.

Manager NEM Real Time Operations
114604RESERVE NOTICE13/02/2024 02:27:41 PM

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.

An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.

The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024

Manager NEM Real Time Operations
114436INTER-REGIONAL TRANSFER08/02/2024 10:24:54 AM

Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024

At 1015 hrs 08/02/2024 there was a short notice outage of Dapto - Marulan 8 Line


The following constraint set(s) invoked at 1015 hrs 08/02/2024
N-DTMN_8_15M

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114429INTER-REGIONAL TRANSFER07/02/2024 07:06:39 PM

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

At 1850 hrs 07/02/2024 there was an unplanned outage of the South Pine SVC.

The following constraint set(s) invoked at 1855 hrs 07/02/2024
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114407INTER-REGIONAL TRANSFER06/02/2024 09:12:48 PM

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

At 2102 hrs 06/02/2024 there was an unplanned outage of the Greenbank 275kV SVC

The following constraint set(s) invoked at 2110 hrs 06/02/2024
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113654INTER-REGIONAL TRANSFER23/01/2024 03:30:39 AM

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

At 0318 hrs 23/01/2024 there was an unplanned outage of Hazelwood - South Morang No2 500 kV Line.

The following constraint set(s) invoked at 0325 hrs 23/01/2024
V-HWSM

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113416INTER-REGIONAL TRANSFER18/01/2024 03:14:09 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 3 Leg of Directlink .

The following constraint set was invoked at 1510 hrs 18/01/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm