Updates to Victorian system normal stability constraint equations
The Victorian system normal constraint equations that determine Victorian export limits based on transient stability and voltage stability at Heywood for Victoria to South Australia flows will be updated to a revised formulation on 25 July 2016 after 1330 hrs. This revised formulation models the effects of higher flows on Victoria to SA on Heywood and the new series capacitors at Black Range.
The changes are to the following constraint equations :
V::N_NIL_V1
V::N_NIL_V2
V::N_NIL_Q1
V::N_NIL_Q2
V::N_NIL_S1
V::N_NIL_S2
V::N_NIL_SD
V^S_HYCP
Ben Blake
AEMO Operations
Cancellation of Actual (LOR1) condition in the South Australia region - 14/07/16
Cancellation of Actual (LOR1) condition in the South Australia region - 14/07/16
The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice 54507 is cancelled at 2030 hrs 14/07/16
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. 14/07/16
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. 14/07/16.
An Actual LOR1 condition has been declared for the SA Region from 1745 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs
The contingency capacity reserve required is 440 MW
The minimum reserve available is 342 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the South Australia region - 13/07/16
Cancellation of Actual (LOR1) condition in the South Australia region - 13/07/16
The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice 544785 is cancelled at 2100 hrs 13/07/16
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. 13/07/16
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. 13/07/16.
An Actual LOR1 condition has been declared for the SA Region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 2100 hrs
The contingency capacity reserve required is 400 MW
The minimum reserve available is 281 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the South Australia region - Tuesday, 12 July 2016
AEMO ELECTRICITY MARKET NOTICE
Cancellation of Actual (LOR1) condition in the South Australia region - Tuesday, 12 July 2016
The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice No 54458 is cancelled at 1930 hrs Tuesday, 12 July 2016.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. Tuesday, 12 July 2016.
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. Tuesday, 12 July 2016.
An Actual LOR1 condition has been declared for the South Australia Region.
From 1830 hrs to 1930 hrs Tuesday, 12 July 2016
The contingency capacity reserve required is 400 MW
The minimum reserve available is 224 MW
Manager NEM Real Time Operations
Cancellation of the Actual (LOR1) condition in the SA region - 8/07/2016
Cancellation of Actual (LOR1) condition in the SA region - 8/07/2016
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.54371 is cancelled at 2000 hrs 8/07/2016.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA Region - 08 July 2016
Actual Lack Of Reserve Level 1 (LOR1) in the SA Region - 08 July 2016
Update to Market Notice 54370
An Actual LOR1 condition has been declared for the SA Region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The contingency capacity reserve required is 400 MW
The reserve available is 343 MW
Manager NEM Real Time Operations