Market Notices

54248RESERVE NOTICE06/07/2016 07:15:35 PM

Cancellation of the Actual (LOR1) condition in the SA region - 6/7/2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 6/7/2016

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.54247 is cancelled at 1900 hrs 6/7/2016.


Manager NEM Real Time Operations
54247RESERVE NOTICE06/07/2016 06:15:46 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA Region - 06 July 2016

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA Region - 06 July 2016
An Actual LOR1 condition has been declared for the SA Region from 1800 hrs.

The Actual LOR1 condition is forecast to exist until 1930 hrs (or is not forecast in Pre Dispatch)

The contingency capacity reserve required is 400 MW

The minimum reserve available is 337 MW


Manager NEM Real Time Operations
54239MARKET SYSTEMS06/07/2016 03:39:11 PM

CHG0039751 : Planned Software Upgrade - NSW External MarketNet Firewall

Change Number: CHG0039751

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Firewall

Change Title: Planned Software Upgrade - NSW External MarketNet Firewall

Change Start Date & Time: 14/07/2016 09:30:00 AEST

Change End Date & Time: 14/07/2016 14:00:00 AEST

Outage Start Date & Time: 14/07/2016 09:40:00 AEST

Outage End Date & Time: 14/07/2016 12:00:00 AEST

Change Description:

Vendor recommended the software upgrade be applied to mitigate a number of software bugs and vulnerabilities that may compromise the stability of the firewall.

Environment: Production

Participant Impact and Requirements:

Participants connected via Telstra IPWAN - Marketnet IPWAN will experience at least one disruption lasting 30 seconds as testing is performed from IPWAN post upgrade.

Participants connected via Lan-2-Lan VPN - Participant connected to the NSW VPN gateway (202.44.78.10) will experience 3 disruptions lasting 30 seconds each.
To avoid disruptions, please connect via the QLD VPN gateway (202.44.76.10) prior to the 14 July 2016.

Participants connected via Remote Access VPN (VPN Variable) - who utilise an AEMO RSA token and the AEMO VPN client software to establish their VPN via the AEMO NSW datacenter VPN termination point (202.44.78.8)
will experience three disruptions lasting 30 seconds each.
Participants are advised to establish their VPN client software connections via the alternate AEMO QLD datacenter VPN endpoint (202.44.76.8) prior to this scheduled outage.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54238MARKET SYSTEMS06/07/2016 03:37:31 PM

CHG0039653 : Planned Maintenance - AEMO NSW Core Datacenter Infrastructure

Change Number: CHG0039653

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: Planned Maintenance - AEMO NSW Core Datacenter Infrastructure

Change Start Date & Time: 13/07/2016 18:00:00 AEST

Change End Date & Time: 13/07/2016 23:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:


Change Description:

The AEMO NSW Core Datacenter Network Infrastructure will be undergoing scheduled maintenance.

Environment: Production

Participant Impact and Requirements:

Impact: No impacts are expected.

User Requirements:Participants are advised to be aware of this maintenance work period.

Lan-2-Lan VPN Participants are encouraged to ensure their VPN connections are configured (as per AEMO best practice) to automatically failover between the AEMO VPN datacenter termination points (NSW: 202.44.78.10, QLD: 202.44.76.10) prior to this scheduled maintenance period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54237MARKET SYSTEMS06/07/2016 03:35:49 PM

CHG0039788: Planned System Outage due to maintenance on QLD Internet link

Change Number: CHG0039788

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Wide Area Network

Change Title: Planned System Outage due to maintenance on QLD Internet link

Change Start Date & Time: 11/07/2016 10:00:00 AEST

Change End Date & Time: 11/07/2016 12:00:00 AEST

Outage Start Date & Time: 11/07/2016 10:00:00 AEST

Outage End Date & Time: 11/07/2016 12:00:00 AEST


Change Description:

The AEMO QLD data center internet telecommunications service will experience an outage as part of an upgraded to this service.

Environment: Production

Participant Impact and Requirements:

Impacts and User Requirements

The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - IPWAN Participants - Nil

Lan-2-Lan VPN Participants - Up to 4 x 2 minutes to participants whom have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10)
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

Remote Access VPN Participants - Up to 4 x 2 minutes to participants who utilise an AEMO RSA token and the AEMO VPN client software to establish their VPN via the AEMO QLD datacenter VPN termination point (202.44.76.8)
Note: Participants are encouraged to establish their VPN client software connections via the alternate AEMO NSW datacenter VPN endpoint (202.44.78.8) prior to this scheduled outage.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54236MARKET SYSTEMS06/07/2016 03:26:06 PM

CHG0039615: Planned Maintenance - AEMO NSW Core Datacenter Infrastructure

Change Number: CHG0039615

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: Planned Maintenance - AEMO NSW Core Datacenter Infrastructure

Change Start Date & Time: 07/07/2016 18:00:00 AEST

Change End Date & Time: 07/07/2016 23:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Change Description:

The AEMO NSW Core Datacenter Network Infrastructure will be undergoing scheduled maintenance.

Environment: Production

Participant Impact and Requirements:

Impact: No impacts are expected.

User Requirements:Participants are advised to be aware of this maintenance work period.

Lan-2-Lan VPN Participants are encouraged to ensure their VPN connections are configured (as per AEMO best practice) to automatically failover between the AEMO datacenter VPN termination points (NSW: 202.44.78.10, QLD: 202.44.76.10) prior to this scheduled maintenance period.

Support Information:

Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54177MARKET SYSTEMS29/06/2016 06:46:09 PM

Planned System Change - MSATS Production Mid-Year 2016 - Release 46.85 COMPLETED

Change Number: CHG0039599

Notification issued to: Market Notice


Notification Type: Completed

Change Type: Normal

Service/ Component: Market Settlement and Transfer Solution

Change Title: Planned System Change - MSATS Production Mid-Year 2016 - Release 46.85

Change Description:
Release has been implemented without any issues.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54175MARKET SYSTEMS29/06/2016 04:01:05 PM

CHG0039699: Planned System Outage - QLD Internet link maintenance

Change Number: CHG0039699


Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Wide Area Network

Change Title: Planned System Outage - QLD Internet link maintenance

Change Start Date & Time: 01/07/2016 10:00:00 AEST

Change End Date & Time: 01/07/2016 11:00:00 AEST


Outage Start Date & Time: 01/07/2016 10:00:00 AEST


Outage End Date & Time: 01/07/2016 11:00:00 AEST


Change Description:

The AEMO QLD data center internet telecommunications service will experience an outage as part of an upgraded to this service.

Environment: Production

Participant Impact and Requirements:

The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - IPWAN Participants - Nil

Lan-2-Lan VPN Participants - Upto 1 x 10 minutes to participants whom have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10)
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

Remote Access VPN Participants - Upto 1 x 10 minutes to participants who utilise an AEMO RSA token and the AEMO VPN client software to establish their VPN via the AEMO QLD datacenter VPN termination point (202.44.76.8)
Note: Participants are encouraged to establish their VPN client software connections via the alternate AEMO NSW datacenter VPN endpoint (2
54174MARKET SYSTEMS29/06/2016 03:53:59 PM

CHG0039748: Plannned System Maintenance on Market Settlement and Transfer Solutions (MSATS)

RFC Number: CHG0039748

Notification issued to: Market Notice

Notification Type: Initial

Service/ Component: Market Settlement and Transfer Solutions (MSATS)

Change Title: Plannned System Maintenance on Market Settlement and Transfer Solutions (MSATS)

Change Start Date & Time: 06/07/2016 17:30:00 AEST
Change End Date & Time: 06/07/2016 19:30:00 AEST


Outage Start Date & Time: 06/07/2016 17:30:00 AEST

Outage End Date & Time: 06/07/2016 19:30:00 AEST


Change Description:

Electricity MSATS Production Site Transfer (NSW to QLD Site) will be carried out to allow maintenance work on the alternate site.

Environment: Production

Participant Impact and Requirements:

Awareness of this outage. Access to all parts of the MSATS system may be interrupted during the outage period. Access should be attempted outside these times.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
*Change times specified are in AEST
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm