Market Notices

116293MARKET SYSTEMS23/04/2024 03:15:21 PM

CHG0088931 | Production | Planned System Maintenance activity.

Change Number: CHG0088931
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: EMS NEM - Network Outage Scheduler (NOS)
Change Title: Planned System Maintenance activity.

Change Start Date & Time: 29/04/2024 11:00:00 AEST
Change End Date & Time: 29/04/2024 12:00:00 AEST
Outage Start Date & Time: 29/04/2024 11:00:00 AEST
Outage End Date & Time: 29/04/2024 12:00:00 AEST

Environment: Production
Participant Impact and Requirements: Network Outage Schedular (NOS) will be out of service during the maintenance activity. Please log off from NOS website during the outage. Users will have to log back in once the outage is completed. Please contact your NOS admin or AEMO support hub if your NOS account has been locked out after this change.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
     
116280MARKET INTERVENTION23/04/2024 05:48:19 PM

Update - Direction - SA Region - 22/04/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 22/04/2024

Refer Market Notice 116263

The AEMO intervention event that commenced from interval ending 1205 hrs on 22/04/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
     
116277MARKET INTERVENTION23/04/2024 01:06:47 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0400 hrs 24/04/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116273MARKET SYSTEMS22/04/2024 02:59:52 PM

CHG0088831 | Completed | Production | Identity Service Config Update in Production.

Change Number: CHG0088831

Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal

Service/Component: Identity Service (IDS)

Change Title: Identity Service Config Update in Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
116267MARKET SYSTEMS22/04/2024 11:44:45 AM

CHG0088138 | Completed | Production | Brisbane MarketNet Firewall Refresh

Change Number: CHG0088138

Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal

Service/Component: Firewall
Change Title: Brisbane MarketNet Firewall Refresh

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.

     
116266MARKET INTERVENTION22/04/2024 02:00:32 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 21/04/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 21/04/2024

Refer Market Notice 116232

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs 22/04/2024

Manager NEM Real Time Operations
     
116263MARKET INTERVENTION22/04/2024 12:06:20 PM

Direction - SA region 22/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 22/04/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1205 hrs on 22/04/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
     
116259MARKET SYSTEMS22/04/2024 10:28:16 AM

CHG0088121 | Completed | Production | Production MSATS Lifecycle Maintenance


Change Number: CHG0088121

Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Production MSATS Lifecycle Maintenance

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.

     
116258MARKET INTERVENTION22/04/2024 10:25:53 AM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116234

The synchronous generating units currently expected to be synchronised in SA from 0001 hrs 23/04/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1200 hrs 22/04/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.