Market Notices

101942MARKET INTERVENTION26/09/2022 02:43:56 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 27/09/2022 will be inadequate to maintain a secure operating state in SA.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 26/09/2022, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
101940MARKET INTERVENTION26/09/2022 01:54:34 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 27/09/2022 will be inadequate to maintain a secure operating state in SA.

AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
101936MARKET INTERVENTION25/09/2022 05:00:17 PM

Cancellation - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in SA region

Refer Market Notice 101920

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1700 hrs 25/09/2022.

Manager NEM Real Time Operations
101920MARKET INTERVENTION25/09/2022 12:54:16 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 26/09/2022 will be inadequate to maintain a secure operating state in SA.

AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
101919MARKET INTERVENTION24/09/2022 05:25:58 PM

Cancellation - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in SA region

Refer Market Notice 101901

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1715 hrs 24/09/2022.

Manager NEM Real Time Operations
101904MARKET INTERVENTION24/09/2022 04:09:14 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA Region - 23/09/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA Region - 23/09/2022

Refer Market Notice 101865

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs 24/09/2022

Manager NEM Real Time Operations
101901MARKET INTERVENTION24/09/2022 02:53:10 PM

Update - Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in South Australia (SA) Region

Refer Market Notice 101899

The synchronous generating units currently expected to be synchronised in SA from 0730 hrs 25/09/2022 will be inadequate to maintain a secure operating state in SA.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 24/09/2022, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
101899MARKET INTERVENTION24/09/2022 02:21:49 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units currently expected to be synchronised in SA from 0730 hrs 25/09/2022 will be inadequate to maintain a secure operating state in SA.

AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
101865MARKET INTERVENTION23/09/2022 05:04:43 PM

Direction - SA Region 23/09/2022

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 23/09/2022

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 23/09/2022.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations