116732SETTLEMENTS RESIDUE20/05/2024 06:30:21 PM

[EventId:202405201830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 May 2024 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 20 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 May 2024.

Refer to market notice: 116731

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 20 May 2024.

This is an AEMO autogenerated Market Notice.
     
116731SETTLEMENTS RESIDUE20/05/2024 05:30:23 PM

[EventId:202405201730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 May 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 20 May 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 May 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 20 May 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
116727MARKET SYSTEMS20/05/2024 03:52:06 PM

CHG0089836 | Pre-Production | Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Change Number: CHG0089836
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.

Change Start Date & Time: 11/06/2024 10:00:00 AEST
Change End Date & Time: 11/06/2024 17:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: AEMO's FRC Gas Hub web services need to have their server certificates updated every year with new certificates to replace the xpiring one.

Participants connecting to these endpoints or receiving requests from AEMO's FRC Gas Hub platforms and have authorisation mechanisms like certificate fingerprinting in place will notice a change in AEMO's server's certificate fingerprint and will need to update their systems accordingly.

The certificate relates to "FBS-Test-Hub.aemo.com.au" certificate and relates to the following domains.
FBS-Test-Hub.aemo.com.au
apis.preprod.aemo.com.au
preprodhub.aemo.com.au
preprod.frchub.net
apis.preprod.marketnet.net.au
preprodhub.marketnet.net.au

Participants WILL need to update the profile that communicates with the above domains.

This will need to be done to avoid the inability to send messages to the relay.

The certificates can be downloaded from the link below:
https://www.digicert.com/secure/download-certificate/m7lnm6qjq6lgqn5kn228qt11d6x9qxv
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
     
116719MARKET SYSTEMS20/05/2024 10:34:23 AM

CHG0089648 | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 16 May until 12pm (EST)

Change Number: CHG0089648
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 16 May until 12pm (EST)

Change Start Date & Time: 16/05/2024 09:00:00 AEST
Change End Date & Time: 16/05/2024 12:00:00 AEST
Outage Start Date & Time: 16/05/2024 09:00:00 AEST
Outage End Date & Time: 16/05/2024 12:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: Services may be unavailable while maintenance is in progress
Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
116715PRICES UNCHANGED19/05/2024 03:50:26 PM

[EventId:202405191520_confirmed] Prices for interval 19-May-2024 15:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024

PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:20.

In accordance with Market Notice 116704 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116714PRICES UNCHANGED19/05/2024 03:49:26 PM

[EventId:202405191545_confirmed] Prices for interval 19-May-2024 15:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024

PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:45.

In accordance with Market Notice 116709 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116713PRICES UNCHANGED19/05/2024 03:48:15 PM

[EventId:202405191540_confirmed] Prices for interval 19-May-2024 15:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024

PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:40.

In accordance with Market Notice 116708 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116712PRICES UNCHANGED19/05/2024 03:47:17 PM

[EventId:202405191535_confirmed] Prices for interval 19-May-2024 15:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024

PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:35.

In accordance with Market Notice 116707 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116711PRICES UNCHANGED19/05/2024 03:46:21 PM

[EventId:202405191530_confirmed] Prices for interval 19-May-2024 15:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024

PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:30.

In accordance with Market Notice 116706 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.