AEMO Intervention Event intervention price dispatch intervals - 09/10/17- revised expected end time
AEMO Intervention Event intervention price dispatch intervals - 09/10/17- revised expected end time
Refer AEMO Electricity Market Notice no. 59400, 59411 and 59429.
An AEMO Intervention Event has been implemented by issuing a direction to maintain the power system in a secure operating state.
The AEMO Intervention Event commenced in the 2000 hrs 09/10/2017 dispatch interval and is forecast to apply until 0700 hrs 11/10/2017.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals. The direction is expected to affect dispatch quantities for intervention pricing purposes from the 2100 hrs 09/10/17 dispatch interval.
Manager NEM Real Time Operations
Update Direction - South Australia Region 09/10/17 - revised expected end time
Update Direction - South Australia Region 09/10/17 - revised expected end time
Refer AEMO Electricity Market Notice 59400 and 59411
In accordance with section 116 of the National Electricity Law AEMO has issued a direction to a participant in the South Australia region.
The direction was necessary to maintain the power system in a secure operating state.
The direction was issued at 2000 hrs 09/10/2017 and is expected to stay in place until 0700 hrs 11/10/2017.
Manager NEM Real Time Operations
AEMO Intervention Event intervention price dispatch intervals - 10/10/17
AEMO Intervention Event intervention price dispatch intervals - 10/10/17
Refer AEMO Electricity Market Notice no. 59423.
An AEMO Intervention Event has been implemented by issuing a direction to maintain the power system in a secure operating state.
The AEMO Intervention Event commenced in the 2130 hrs dispatch interval and is forecast to apply until 0600 hrs 11/10/17.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals. The direction is expected to affect dispatch quantities for intervention pricing purposes from the 2230 hrs dispatch interval.
Manager NEM Real Time Operations
Direction - South Australia Region 10/10/17
Direction - South Australia Region 10/10/17
In accordance with section 116 of the National Electricity Law AEMO has issued a direction to a participant in the South Australia region.
The direction was necessary to maintain the power system in a secure operating state.
The direction was issued at 2130 hrs and is expected to stay in place until 0600 hrs 11/10/17
Manager NEM Real Time Operations
AEMO Intervention Event intervention price dispatch intervals - 10/10/17 - revised expected end time
AEMO Intervention Event intervention price dispatch intervals - 10/10/17 - revised expected end time
Refer AEMO Electricity Market Notice No. 59402, 59406 and 59415
An AEMO Intervention Event has been implemented by issuing a direction to maintain the power system in a secure operating state.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
This AEMO Intervention Event commenced in the 0600 hrs 10/10/2017 dispatch interval and is forecast to apply until 0600 hrs 11/10/2017
This Intervention pricing will be implemented from the 2230 hrs 10/10/2017 dispatch interval for this direction until the end of the AEMO Intervention Event.
Manager NEM Real Time Operations
Update Direction - South Australia Region 10/10/17 - revised expected end time
Update Direction - South Australia Region 10/10/17 - revised expected end time
Refer AEMO Electricity Market Notice 59406
In accordance with section 116 of the National Electricity Law AEMO has issued a direction to a participant in the South Australia region.
The direction was necessary to maintain the power system in a secure operating state.
The direction was issued at 0600 hrs 10/10/2017 and is expected to stay in place until 0600 hrs 11/10/2017
Manager NEM Real Time Operations
Update AEMO Intervention Event intervention price dispatch intervals - 09/10/17 - revised expected end time
Update AEMO Intervention Event intervention price dispatch intervals - 09/10/17 - revised expected end time
Refer AEMO Electricity Market Notice 59400 and 59411
An AEMO Intervention Event has been implemented by issuing a direction to maintain the power system in a secure operating state.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
The AEMO Intervention Event commenced in the 2000 hrs 09/10/2017 dispatch interval and is forecast to apply until 0600 hrs 11/10/2017
Intervention pricing will be implemented from the 2100 hrs 09/10/17 dispatch interval until the end of the AEMO Intervention Event.
Manager NEM Real Time Operations
Update Direction - South Australia Region 09/10/17 - revised expected end time
Update Direction - South Australia Region 09/10/17 - revised expected end time
Refer AEMO Electricity Market Notice 59400
In accordance with section 116 of the National Electricity Law AEMO has issued a direction to a participant in the South Australia region.
The direction was necessary to maintain the power system in a secure operating state.
The direction was issued at 2000 hrs 09/10/2017 and is expected to stay in place until 0600 hrs 11/10/2017.
Manager NEM Real Time Operations
AEMO Intervention Event intervention price dispatch intervals - 10/10/17
AEMO Intervention Event - Intervention price dispatch intervals - 10/10/17
Refer AEMO Electricity Market Notice No. 49502 and 49506.
An AEMO Intervention Event has been implemented by issuing a direction to maintain the power system in a secure operating state.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
This AEMO Intervention Event commenced in the 0600 hrs dispatch interval and is forecast to apply until 1730 hrs 11/10/17
This Intervention pricing will be implemented from the 0000 hrs 11/10/17 dispatch interval for this direction until the end of the AEMO Intervention Event.
Manager NEM Real Time Operations