Market Notices

116579RECLASSIFY CONTINGENCY10/05/2024 05:54:50 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 10/05/2024 17:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 116578

Auto-generated on behalf of Manager NEM Real Time Operations
     
116578RECLASSIFY CONTINGENCY10/05/2024 04:51:05 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 10/05/2024 16:51 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
116577MARKET INTERVENTION10/05/2024 04:56:42 PM

Direction - SA region 10/05/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 10/05/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 10/05/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
     
116575MARKET SYSTEMS10/05/2024 02:49:28 PM

CHG0089536 | Production | Urgent NSW Marketnet Router Replacement

Change Number: CHG0089536

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: Urgent NSW Marketnet Router Replacement

Change Start Date & Time: 11/05/2024 10:00:27 AEST
Change End Date & Time: 11/05/2024 14:00:27 AEST
Outage Start Date & Time: 11/05/2024 10:00:26 AEST
Outage End Date & Time: 11/05/2024 12:00:26 AEST

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from NSW to QLD Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point (202.44.76.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as DNS entry will be updated to remove NSW IP.

GASHUB: No impact is expected as GASHUB is currently operating out of BNE Datacenter.

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
116574MARKET INTERVENTION10/05/2024 02:17:13 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116573

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 11/05/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 10/05/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116573MARKET INTERVENTION10/05/2024 12:16:25 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0930 hrs 11/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116572RECLASSIFY CONTINGENCY10/05/2024 10:13:53 AM

Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - NEM regions.

AEMO ELECTRICITY MARKET NOTICE.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely Severe Space Weather Watch in the NEM regions.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
     
116568RECLASSIFY CONTINGENCY10/05/2024 06:01:54 PM

Cancellation - Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to planned outage : Ross 275 kV SVC and Ross 275/132 kV No. 4 transformer - Qld region.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation - Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to planned outage.

AEMO considers the occurrence of a non-credible contingency event due to planned outage advised in AEMO Electricity Market Notice 116557 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Region: Qld

Elements: Ross 275 kV SVC and Ross 275/132 kV No. 4 transformer

Cancellation time: 1800 hrs 10/05/2024

Constraint set(s) invoked:
Nil

Manager NEM Real Time Operations
     
116563MARKET SYSTEMS09/05/2024 03:10:22 PM

CHG0089532 | Cancelled | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 11.00am Thursday 9 May until 1pm (EST)

Change Number: CHG0089532

Notification issued to: Market Notice

Notification Type: Cancelled

Change Type: Normal

Service/ Component: Gas Supply Hub

Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 11.00am Thursday 9 May until 1pm (EST)

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
     